EX35.39 - Toronto Police Service - 2018 Capital Budget Variance Report - Period Ending March 31, 2018

Decision Type:
ACTION
Status:
Adopted
Wards:
All

City Council Decision

City Council on June 26, 27, 28 and 29, 2018, adopted the following:

 

1.  City Council approve a 2018 cash flow transfer of $1.34 million to the Enterprise Business Intelligence project to offset the 2016 unspent carry forward of $1.34 million that is required in 2018 to complete the Enterprise Business Intelligence project, from the following 2018 cash flow sources:

 

a.  $750,000 from the Conducted Energy Weapon project;

 

b.  $94,000 from the Radio Replacement project; and

 

c.  $500,000 from the Parking Handheld Administrative Penalty System project.

 

2.  City Council approve the advancement of $3.49 million in 2019 cash flow to 2018 for the Peer to Peer site project, funded by the deferral of the following 2018 cash flows:

 

a.  $2.6 million from Debt and $797,000 from Development Charges from the 54/55 Amalgamation project; and

 

b.  $100,000 from the State of Good Repair project.

 

3.  City Council approve the advancement of 2020 cash flow to 2018 in the amount of $200,000 for 32 Division project (part of facility realignment) funded by the deferral of the 2018 cash flow for the same amount from 54/55 Amalgamation project.

Background Information (Committee)

(May 28, 2018) Letter from the Budget committee on Toronto Police Service - 2018 Capital Budget Variance Report - Period Ending March 31, 2018
https://www.toronto.ca/legdocs/mmis/2018/ex/bgrd/backgroundfile-115836.pdf
(May 17, 2018) Report and Appendix A from the Chair, Toronto Police Services Board on Toronto Police Service - 2018 Capital Budget Variance Report - Period Ending March 31, 2018
https://www.toronto.ca/legdocs/mmis/2018/ex/bgrd/backgroundfile-115837.pdf

Motions (City Council)

Motion to Adopt Item (Carried)

Vote (Adopt Item) Jun-26-2018 3:04 PM

Result: Carried Majority Required - EX35.39 - Adopt the item
Total members that voted Yes: 40 Members that voted Yes are Paul Ainslie, Maria Augimeri, Ana Bailão, Jon Burnside, John Campbell, Christin Carmichael Greb, Josh Colle, Gary Crawford, Joe Cressy, Vincent Crisanti, Janet Davis, Glenn De Baeremaeker, Justin J. Di Ciano, Frank Di Giorgio, Sarah Doucette, John Filion, Paula Fletcher, Mark Grimes, Jim Hart, Stephen Holyday, Jim Karygiannis, Mike Layton, Josh Matlow, Mary-Margaret McMahon, Miganoush Megardichian, Joe Mihevc, Denzil Minnan-Wong, Frances Nunziata (Chair), Cesar Palacio, James Pasternak, Gord Perks, Anthony Perruzza, Jaye Robinson, Neethan Shan, David Shiner, Michael Thompson, John Tory, Lucy Troisi, Jonathan Tsao, Kristyn Wong-Tam
Total members that voted No: 0 Members that voted No are
Total members that were Absent: 5 Members that were absent are Michael Ford, Mary Fragedakis, Michelle Holland, Norman Kelly, Giorgio Mammoliti

Declared Interests (City Council)

The following member(s) declared an interest:

Councillor Norman Kelly - as his wife is a civilian member of the Toronto Police Service.

EX35.39 - Toronto Police Service - 2018 Capital Budget Variance Report - Period Ending March 31, 2018

Decision Type:
ACTION
Status:
Adopted
Wards:
All

Committee Recommendations

The Executive Committee recommends that:

 

1.  City Council approve a 2018 cash flow transfer of $1.34 million to the Enterprise Business Intelligence (E.B.I.) project to offset the 2016 unspent carry forward of $1.34 million (M) that is required in 2018 to complete the Enterprise Business Intelligence project, from the following 2018 cash flow sources:

 

a.  $750,000 from the Conducted Energy Weapon project;

 

b.  $94,000 from the Radio Replacement project; and

 

c.  $500,000 from the Parking Handheld Administrative Penalty System project.

 

2.  City Council approve the advancement of $3.49 million in 2019 cash flow to 2018 for the Peer to Peer site project, funded by the deferral of the following 2018 cash flows:

 

a.  $2.6 million from Debt and $797,000 from Development Charges from the 54/55 Amalgamation project; and

 

b.  $100,000 from the State of Good Repair project.

 

3.  City Council approve the advancement of 2020 cash flow to 2018 in the amount of $200,000 for 32 Division project (part of facility realignment) funded by the deferral of the 2018 cash flow for the same amount from 54/55 Amalgamation project.

Origin

(May 28, 2018) Letter from the Budget Committee

Summary

The purpose of this report is to provide the Budget Committee with the Toronto Police Service’s 2018 capital budget variance report for the period ending March 31, 2018

Background Information

(May 28, 2018) Letter from the Budget committee on Toronto Police Service - 2018 Capital Budget Variance Report - Period Ending March 31, 2018
https://www.toronto.ca/legdocs/mmis/2018/ex/bgrd/backgroundfile-115836.pdf
(May 17, 2018) Report and Appendix A from the Chair, Toronto Police Services Board on Toronto Police Service - 2018 Capital Budget Variance Report - Period Ending March 31, 2018
https://www.toronto.ca/legdocs/mmis/2018/ex/bgrd/backgroundfile-115837.pdf

Motions

1 - Motion to Adopt Item moved by Councillor Gary Crawford (Carried)