Item - 2012.EX25.9
Tracking Status
- City Council adopted this item on November 27, 28 and 29, 2012 with amendments.
- This item was considered by the Executive Committee on November 19, 2012 and adopted without amendment. It will be considered by City Council on November 27, 28 and 29, 2012.
- See also BU31.1
- See also By-law 1636-2012
EX25.9 - 2013 Rate Supported Budgets - Toronto Water and 2013 Water and Wastewater Rates and Service Fees (Item BU31.1)
- Decision Type:
- ACTION
- Status:
- Amended
- Wards:
- All
City Council Decision
City Council on November 27, 28 and 29, 2012, adopted the following:
1. City Council direct that:
a. Effective January 1, 2013, the combined water and wastewater rates charged to metered consumers shall be as shown below and in Appendix B attached to the report (November 6, 2012) from the Acting Deputy City Manager and Chief Financial Officer and the General Manager, Toronto Water:
Annual Consumption | Paid on or before the due date, $/m3 | Paid after the due date, $/m3 |
Block 1 - All consumers, including Industrial consumption of first 6,000 m3 ("Block 1 rate") | $2.7137 | $2.8567 |
Block 2 - Industrial process – use water consumption over 6,000 m3, representing 30% reduction from the Block 1 Rate ("Block 2 rate') | $1.8996 | $1.9996 |
b. The water and wastewater rates charged to flat rate consumers be increased by 9 percent, effective January 1, 2013, to the rates shown in Appendix B attached to the report (November 6, 2012) from the Acting Deputy City Manager and Chief Financial Officer and the General Manager, Toronto Water;
c. Effective January 1, 2013, the water and wastewater service fees shall be as shown in Appendix C attached to the report (November 6, 2012) from the Acting Deputy City Manager and Chief Financial Officer and the General Manager, Toronto Water; and
d. Effective January 1, 2013, the fee basis for water drawn from unmetered hydrants, less than or equal to 50 cubic metre, be changed from "Flat Rate" to "Per 50 cubic metres" and the fee amount be changed from "$100" to "50 m3 at Block 1 Water Rate" as set out in Appendix C - Schedule 2, Water Services, Ref. No. 18, attached to the report (November 6, 2012) from the Acting Deputy City Manager and Chief Financial Officer and the General Manager, Toronto Water.
2. City Council, with respect to the City's industrial waste surcharge program:
a. Amend Municipal Code Chapter 681, Sewers as necessary to include Total Kjeldahl Nitrogen (TKN) as a treatable parameter including adding TKN as a treatable parameter in subsection 681-6B(1) and as a parameter in subsection 681-2C(1)(b) and (c);
b. Charge effective January 1, 2013, a fee of $800 for the establishment of any new industrial waste surcharge agreement, as set out in Appendix C - Schedule 3, Wastewater Services, Ref. No. 20 attached to the report (November 6, 2012) from the Acting Deputy City Manager and Chief Financial Officer and the General Manager, Toronto Water;
c. Approve effective January 1, 2013, the rates for treatable parameters applying to industrial waste surcharge agreements as shown below and in Appendix C - Schedule 3, Wastewater Services, Ref. No. 1.1, 1.2, 1.3 and 1.4 attached to the report (November 6, 2012) from the Acting Deputy City Manager and Chief Financial Officer and the General Manager, Toronto Water:
Parameter | Rate ($/kg) |
Biochemical Oxygen Demand (BOD) or Phenolics (4AAP) | $0.62 |
Total Suspended Solids (TSS) | $0.60 |
Total Phosphorus (TP) | $1.69 |
Total Kjeldahl Nitrogen (TKN) | $1.18 |
d. Effective January 1, 2013, Type1 ODF Formula – Unit Cost per Kilogram (see Appendix D to the report (November 6, 2012) from the Acting Deputy City Manager and Chief Financial Officer and the General Manager, Toronto Water, hereafter called the "Type 1 Formula") be used for the calculation of surcharge fees, modified such that the calculation of surcharge fees be applied only to the parameter that exceeds the Municipal Code Chapter 681, Sewers limits the most, which implements Council's decision on Public Works and Infrastructure Committee (Item PW18.1).
3. City Council, with respect to assistance for low-income seniors and low-income disabled persons:
a. Set the rebate for eligible low-income seniors and low-income disabled persons at a rate of $0.8141 /m3, effective January 1, 2013, representing a 30% reduction from the Block 1 rate (paid on or before the due date).
Toronto Water - 2013 Recommended Operating Budget
4. City Council approve the 2013 Recommended Operating Budget for Toronto Water of $394.395 million gross and $546.402 million in capital-from-current contribution, comprised of the following services:
| Gross |
| Net |
Service | ($000s) |
| ($000s) |
Water Supply and Treatment | 69,992.4 |
| 0 |
Wastewater Treatment | 110,775.0 |
| 0 |
District Operations | 89,760.1 |
| 0 |
Water Infrastructure Management | 9,807.7 |
| 0 |
Business Operations Management | 18,361.2 |
| 0 |
Operational Support | 40,384.4 |
| 0 |
Program Support | 55,313.8 |
| 0 |
Capital-from-Current Contributions | 546,402.5 |
| 0 |
Total Program Budget | 940,797.1 |
| 0 |
5. City Council approve Toronto Water's services and 2013 proposed service levels, as outlined on page 6 of the 2013 Recommended Operating Budget for Toronto Water and associated staff complement of 1,724.8.
Toronto Water - 2013 Recommended Capital Budget
6. City Council approve the 2013 Recommended Capital Budget for Toronto Water with a total project cost of $708.782 million, and 2013 cash flow of $657.266 million and future year commitments of $2.059 billion comprised of the following:
a. New Cash Flow Funding for:
i. 109 new / change in scope sub-projects with a 2013 total project cost of $708.782 million that requires cash flow of ($1.966 million) in 2013 and a future year cash flow commitment of $242.619 million in 2014; $131.968 million in 2015, $95.697 million in 2016, $93.550 million in 2017, ($20.057 million) in 2018, ($1.509 million) in 2019; $55.292 million in 2020, $42.308 million in 2021, and $70.880 million in 2022;
ii. 76 previously approved sub-projects with a 2013 cash flow of $527.842 million; and a future year cash flow commitment of $386.809 million in 2014; $334.712 million in 2015, $206.080 million in 2016, $115.026 million in 2017, $123.831 million in 2018, $102.395 million in 2019; $45.303 million in 2020, and $33.932 million in 2021; and
b. 2012 approved cash flow for 83 previously approved sub-projects with carry forward funding from 2012 into 2013 totaling $131.390 million.
7. City Council approve the 2014-2022 Recommended Capital Plan for Toronto Water totaling $5.601 billion in project estimates, comprised of $113.152 million in 2014; $316.637 million in 2015; $501.763 million in 2016; $618.179 million in 2017; $723.361 million in 2018; $777.748 million in 2019; $817.309 million in 2020; $880.760 million in 2021; and $851.607 million in 2022.
8. City Council consider operating costs of $5.675 million net in 2013, $2.432 million net in 2014; $0.347 million net in 2015; $0.247 million net in 2016; $5.372 million net in 2017; $5.530 million net in 2018; and $0.053 million net in 2019; emanating from the approval of the 2013 Recommended Capital Budget for Toronto Water for inclusion in the 2013 and future year operating budgets.
9. City Council request the General Manager, Toronto Water to report through the 2014 budget process on ways to include in the 2014-18 Basement Flooding Program, funding for the eligible capital projects arising from the Class Environmental Assessments in the five remaining basement flooding areas (1, 2, 21, 23, 34).
10. City Council make the necessary amendments to Municipal Code Chapter 441 - Fees and Charges, Municipal Code Chapter 849 - Water and Sewage Services and Utility Bill, and Municipal Code Chapter 681- Sewers, and any other necessary Municipal Code Chapters as may be required, to give effect to Council's decision.
11. City Council authorize the City Solicitor to introduce any necessary Bills required to implement Council's decision, subject to any necessary refinements, including stylistic, format and organization, as may be identified by the City Solicitor, the Deputy City Manager and Chief Financial Officer and General Manager, Toronto Water.
12. City Council authorize the appropriate City officials and directed to take the necessary actions to give effect Council's decision.
City Council Decision Advice and Other Information
City Council considered Items EX25.9 and PW18.1 together.
Background Information (Committee)
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52183.htm
(November 7, 2012) Presentation from the General Manager, Toronto Water on Toronto Water 2013 Recommended Operating Budget and 2013 – 2022 Recommended Capital Plan 2013 Recommended Water Rate
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52179.pdf
(November 6, 2012) Report with Appendix A from the Acting Deputy City Manager and Chief Financial Officer and the General Manager, Toronto Water on 2013 Water and Wastewater Rates and Service Fees
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52168.pdf
(November 6, 2012) Appendix B
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52165.pdf
(November 6, 2012) Appendix C
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52166.pdf
(November 6, 2012) Appendix D
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52167.pdf
(November 7, 2012) 2013 Staff Recommended Capital Budget - Toronto Water
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52172.pdf
(November 7, 2012) 2013 Staff Recommended Capital Budget - Toronto Water - Appendix 3
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52173.pdf
(November 7, 2012) 2013 Staff Recommended Capital Budget - Toronto Water - Appendix 4
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52174.pdf
(November 7, 2012) 2013 Staff Recommended Capital Budget - Toronto Water - Appendix 5
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52175.pdf
(November 7, 2012) 2013 Toronto Water Capital Budget Briefing Note #1 - Basement Flooding Protection Program - Project List: 2013 to 2017
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52170.pdf
(November 12, 2012) Wrap-Up Notes to Budget Committee - 2013 Recommended Capital Budget Rate Supported Programs
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52182.pdf
(November 7, 2012) 2013 Staff Recommended Operating Budget - Toronto Water
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52176.pdf
(November 7, 2012) 2013 Staff Recommended Operating Budget - Toronto Water - Appendix 3
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52177.pdf
(November 7, 2012) 2013 Staff Recommended Operating Budget - Toronto Water - Appendix 4
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52178.pdf
(November 7, 2012) 2013 Toronto Water Operating Budget Briefing Note #1 - Changes to Industrial Waste Surcharge Program
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52169.pdf
(November 12, 2012) Wrap-Up Notes to Budget Committee - 2013 Recommended Operating Budget Rate Supported Programs
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52181.pdf
(November 2, 2012) Public Notice - 2013 Rate Supported Budgets - Toronto Water and 2013 Water and Wastewater Rates and Service Fees
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52171.pdf
(November 2, 2012) Public Notice - Appendix A
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52163.pdf
(November 2, 2012) Public Notice - Appendix B
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52164.pdf
(November 1, 2012) Report from the Acting Deputy City Manager and Chief Financial Officer and the General Manager, Toronto Water on 2013 Water and Wastewater Rates and Service Fees - Notice of Pending Report
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52162.pdf
(November 19, 2012) Wrap-Up Notes to Executive Committee - 2013 Recommended Capital Budget Rate Supported Programs
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52287.pdf
(November 19, 2012) Wrap-Up Notes to Executive Committee - 2013 Recommended Operating Budget Rate Supported Programs
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52288.pdf
Communications (City Council)
https://www.toronto.ca/legdocs/mmis/2012/cc/comm/communicationfile-33548.pdf
Motions (City Council)
That:
1. City Council delete Executive Committee Recommendation 2.d.
Recommendation to be deleted:
d. Effective January 1, 2013, Type1 ODF Formula – Unit Cost per Kilogram (see Appendix D to the report (November 6, 2012) from the Acting Deputy City Manager and Chief Financial Officer and the General Manager, Toronto Water, hereafter called the "Type 1 Formula") be used for the calculation of surcharge fees, modified such that the calculation of surcharge fees be applied only to the parameter that exceeds the Municipal Code Chapter 681, Sewers limits the most, which implements the Recommendations from the Public Works and Infrastructure Committee (Item PW18.1).
and replace it with the following:
d. Subject to Recommendation 2(e) below, effective January 1, 2013, the Type 1 ODF Formula – Unit Cost per Kilogram (see Appendix D to the report (November 6, 2012) from the Acting Deputy City Manager and Chief Financial Officer and the General Manager, Toronto Water, hereinafter called the "Type 1 Formula") be used for the calculation of industrial waste surcharge fees in the City's industrial waste surcharge agreements.
2. City Council amend Recommendation 2 by adding the following new section:
e. The following annual adjustment factors be applied to the Type 1 Formula to allow for the gradual transition to full cost recovery over a six-year period in order to allow companies sufficient time to make changes to their internal processes and budget forecasts:
Year | Adjustment Factor | Year | Adjustment Factor |
2013 | 0.75 | 2016 | 0.90 |
2014 | 0.80 | 2017 | 0.95 |
2015 | 0.85 | 2018 | 1.00 |
That City Council request the General Manager, Toronto Water to report through the 2014 budget process on ways to include in the 2014-18 Basement Flooding Program, funding for the eligible capital projects arising from the Class Environmental Assessments in the five remaining basement flooding areas (1, 2, 21, 23, 34).
Vote (Amend Item (Additional)) Nov-29-2012 11:20 AM
| Result: Carried | Majority Required - EX25.9 - Davis - motion 2 |
|---|---|
| Total members that voted Yes: 35 | Members that voted Yes are Maria Augimeri, Ana Bailão, Shelley Carroll, Raymond Cho, Josh Colle, Gary Crawford, Vincent Crisanti, Janet Davis, Glenn De Baeremaeker, Mike Del Grande, Frank Di Giorgio, Sarah Doucette, John Filion, Mary Fragedakis, Norman Kelly, Mike Layton, Chin Lee, Gloria Lindsay Luby, Josh Matlow, Pam McConnell, Mary-Margaret McMahon, Joe Mihevc, Peter Milczyn, Denzil Minnan-Wong, Frances Nunziata (Chair), Cesar Palacio, John Parker, James Pasternak, Gord Perks, Jaye Robinson, David Shiner, Karen Stintz, Michael Thompson, Adam Vaughan, Kristyn Wong-Tam |
| Total members that voted No: 5 | Members that voted No are Paul Ainslie, Doug Ford, Rob Ford, Mark Grimes, Doug Holyday |
| Total members that were Absent: 5 | Members that were absent are Michelle Berardinetti, Paula Fletcher, Giorgio Mammoliti, Ron Moeser, Anthony Perruzza |
That City Council adopt the Item as amended, only as it pertains to the Blue Flag program.
Vote (Adopt Item as Amended) Nov-29-2012 11:24 AM
| Result: Carried | Majority Required - EX25.9 - Adopt item as amended as it pertains to the Blue Flag Program |
|---|---|
| Total members that voted Yes: 37 | Members that voted Yes are Paul Ainslie, Maria Augimeri, Ana Bailão, Shelley Carroll, Raymond Cho, Josh Colle, Gary Crawford, Vincent Crisanti, Janet Davis, Glenn De Baeremaeker, Mike Del Grande, Frank Di Giorgio, Sarah Doucette, John Filion, Rob Ford, Mary Fragedakis, Mark Grimes, Doug Holyday, Norman Kelly, Chin Lee, Gloria Lindsay Luby, Josh Matlow, Pam McConnell, Mary-Margaret McMahon, Joe Mihevc, Peter Milczyn, Denzil Minnan-Wong, Frances Nunziata (Chair), Cesar Palacio, John Parker, James Pasternak, Jaye Robinson, David Shiner, Karen Stintz, Michael Thompson, Adam Vaughan, Kristyn Wong-Tam |
| Total members that voted No: 0 | Members that voted No are |
| Total members that were Absent: 8 | Members that were absent are Michelle Berardinetti, Paula Fletcher, Doug Ford, Mike Layton, Giorgio Mammoliti, Ron Moeser, Gord Perks, Anthony Perruzza |
That City Council adopt the Item as amended, excluding the Blue Flag Program.
Vote (Adopt Item as Amended) Nov-29-2012 11:25 AM
| Result: Carried | Majority Required - EX25.9 - Adopt balance of item as amended |
|---|---|
| Total members that voted Yes: 39 | Members that voted Yes are Paul Ainslie, Maria Augimeri, Ana Bailão, Raymond Cho, Josh Colle, Gary Crawford, Vincent Crisanti, Janet Davis, Glenn De Baeremaeker, Mike Del Grande, Frank Di Giorgio, Sarah Doucette, John Filion, Doug Ford, Rob Ford, Mary Fragedakis, Mark Grimes, Doug Holyday, Norman Kelly, Mike Layton, Chin Lee, Gloria Lindsay Luby, Josh Matlow, Pam McConnell, Mary-Margaret McMahon, Joe Mihevc, Peter Milczyn, Denzil Minnan-Wong, Frances Nunziata (Chair), Cesar Palacio, John Parker, James Pasternak, Gord Perks, Jaye Robinson, David Shiner, Karen Stintz, Michael Thompson, Adam Vaughan, Kristyn Wong-Tam |
| Total members that voted No: 1 | Members that voted No are Shelley Carroll |
| Total members that were Absent: 5 | Members that were absent are Michelle Berardinetti, Paula Fletcher, Giorgio Mammoliti, Ron Moeser, Anthony Perruzza |
Declared Interests (City Council)
Councillor Mike Layton - as it relates to the operating budget for Toronto Water's Blue Flag program, as his spouse works for an organization that receives funding to deliver this program.
Councillor Gord Perks - as it relates to the operating budget for Toronto Water's Blue Flag program, as his spouse works for an organization that oversees that program.
EX25.9 - 2013 Rate Supported Budgets - Toronto Water and 2013 Water and Wastewater Rates and Service Fees (Item BU31.1)
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
Committee Recommendations
The Executive Committee recommends that:
1. City Council direct that:
a. Effective January 1, 2013, the combined water and wastewater rates charged to metered consumers shall be as shown below and in Appendix B attached to the report (November 6, 2012) from the Acting Deputy City Manager and Chief Financial Officer and the General Manager, Toronto Water;
Annual Consumption | Paid on or before the due date, $/m3 | Paid after the due date, $/m3 |
Block 1 - All consumers, including Industrial consumption of first 6,000 m3 ("Block 1 rate") | $2.7137 | $2.8567 |
Block 2 - Industrial process – use water consumption over 6,000 m3, representing 30% reduction from the Block 1 Rate ("Block 2 rate') | $1.8996 | $1.9996 |
b. The water and wastewater rates charged to flat rate consumers be increased by 9%, effective January 1, 2013, to the rates shown in Appendix B attached to the report (November 6, 2012) from the Acting Deputy City Manager and Chief Financial Officer and the General Manager, Toronto Water;
c. Effective January 1, 2013, the water and wastewater service fees shall be as shown in Appendix C attached to the report (November 6, 2012) from the Acting Deputy City Manager and Chief Financial Officer and the General Manager, Toronto Water;
d. Effective January 1, 2013, the fee basis for water drawn from unmetered hydrants, less than or equal to 50 cubic metre, be changed from "Flat Rate" to "Per 50 cubic metres" and the fee amount be changed from "$100" to "50 m3 at Block 1 Water Rate" as set out in Appendix C - Schedule 2, Water Services, Ref. No. 18, attached to the report (November 6, 2012) from the Acting Deputy City Manager and Chief Financial Officer and the General Manager, Toronto Water.
2. City Council, with respect to the City's industrial waste surcharge program:
a. Amend Municipal Code Chapter 681, Sewers as necessary to include Total Kjeldahl Nitrogen (TKN) as a treatable parameter including adding TKN as a treatable parameter in subsection 681-6B(1) and as a parameter in subsection 681-2C(1)(b) and (c);
b. Charge effective January 1, 2013, a fee of $800 for the establishment of any new industrial waste surcharge agreement, as set out in Appendix C - Schedule 3, Wastewater Services, Ref. No. 20 attached to the report (November 6, 2012) from the Acting Deputy City Manager and Chief Financial Officer and the General Manager, Toronto Water;
c. Approve effective January 1, 2013, the rates for treatable parameters applying to industrial waste surcharge agreements as shown below and in Appendix C - Schedule 3, Wastewater Services, Ref. No. 1.1, 1.2, 1.3 and 1.4 attached to the report (November 6, 2012) from the Acting Deputy City Manager and Chief Financial Officer and the General Manager, Toronto Water:
Parameter | Rate ($/kg) |
Biochemical Oxygen Demand (BOD) or Phenolics (4AAP) | $0.62 |
Total Suspended Solids (TSS) | $0.60 |
Total Phosphorus (TP) | $1.69 |
Total Kjeldahl Nitrogen (TKN) | $1.18 |
d. Effective January 1, 2013, Type1 ODF Formula – Unit Cost per Kilogram (see Appendix D to the report (November 6, 2012) from the Acting Deputy City Manager and Chief Financial Officer and the General Manager, Toronto Water, hereafter called the "Type 1 Formula") be used for the calculation of surcharge fees, modified such that the calculation of surcharge fees be applied only to the parameter that exceeds the Municipal Code Chapter 681, Sewers limits the most, which implements the Recommendations from the Public Works and Infrastructure Committee (Item PW18.1).
3. City Council, with respect to assistance for low-income seniors and low-income disabled persons:
a. Set the rebate for eligible low-income seniors and low-income disabled persons at a rate of $0.8141 /m3, effective January 1, 2013, representing a 30% reduction from the Block 1 rate (paid on or before the due date).
Toronto Water - 2013 Recommended Operating Budget
4. City Council approve the 2013 Recommended Operating Budget for Toronto Water of $394.395 million gross and $546.402 million in capital-from-current contribution, comprised of the following services:
| Gross |
| Net |
Service | ($000s) |
| ($000s) |
Water Supply & Treatment | 69,992.4 |
| 0 |
Wastewater Treatment | 110,775.0 |
| 0 |
District Operations | 89,760.1 |
| 0 |
Water Infrastructure Management | 9,807.7 |
| 0 |
Business Operations Management | 18,361.2 |
| 0 |
Operational Support | 40,384.4 |
| 0 |
Program Support | 55,313.8 |
| 0 |
Capital-from-Current Contributions | 546,402.5 |
| 0 |
Total Program Budget | 940,797.1 |
| 0 |
5. City Council approve Toronto Water's services and 2013 proposed service levels, as outlined on page 6 of the 2013 Recommended Operating Budget for Toronto Water and associated staff complement of 1,724.8.
6. City Council consider this report concurrently with the "Sewers By-law Administration – Response to Request for Information" report (September 27, 2012) from the General Manager, Toronto Water.
Toronto Water - 2013 Recommended Capital Budget
7. City Council approve the 2013 Recommended Capital Budget for Toronto Water with a total project cost of $708.782 million, and 2013 cash flow of $657.266 million and future year commitments of $2.059 billion comprised of the following:
a. New Cash Flow Funding for:
i. 109 new / change in scope sub-projects with a 2013 total project cost of $708.782 million that requires cash flow of ($1.966 million) in 2013 and a future year cash flow commitment of $242.619 million in 2014; $131.968 million in 2015, $95.697 million in 2016, $93.550 million in 2017, ($20.057 million) in 2018, ($1.509 million) in 2019; $55.292 million in 2020, $42.308 million in 2021, and $70.880 million in 2022;
ii. 76 previously approved sub-projects with a 2013 cash flow of $527.842 million; and a future year cash flow commitment of $386.809 million in 2014; $334.712 million in 2015, $206.080 million in 2016, $115.026 million in 2017, $123.831 million in 2018, $102.395 million in 2019; $45.303 million in 2020, and $33.932 million in 2021; and
b. 2012 approved cash flow for 83 previously approved sub-projects with carry forward funding from 2012 into 2013 totaling $131.390 million.
8. City Council approve the 2014-2022 Recommended Capital Plan for Toronto Water totaling $5.601 billion in project estimates, comprised of $113.152 million in 2014; $316.637 million in 2015; $501.763 million in 2016; $618.179 million in 2017; $723.361 million in 2018; $777.748 million in 2019; $817.309 million in 2020; $880.760 million in 2021; and $851.607 million in 2022.
9. City Council consider operating costs of $5.675 million net in 2013, $2.432 million net in 2014; $0.347 million net in 2015; $0.247 million net in 2016; $5.372 million net in 2017; $5.530 million net in 2018; and $0.053 million net in 2019; emanating from the approval of the 2013 Recommended Capital Budget for Toronto Water for inclusion in the 2013 and future year operating budgets.
10. City Council make the necessary amendments to Municipal Code Chapter 441 - Fees and Charges, Municipal Code Chapter 849 - Water and Sewage Services and Utility Bill, and Municipal Code Chapter 681- Sewers, and any other necessary Municipal Code Chapters as may be required, to give effect to the Recommendations above.
11. City Council grant authority to the City Solicitor to introduce any necessary Bills required to implement these recommendations, subject to any necessary refinements, including stylistic, format and organization, as may be identified by the City Solicitor, the Deputy City Manager and Chief Financial Officer and General Manager, Toronto Water.
12. City Council authorize the appropriate City officials and directed to take the necessary actions to give effect thereto.
Origin
Summary
The report (November 1, 2012) from the Acting Deputy City Manager and Chief Financial Officer and the General Manager, Toronto Water presents the recommended 2013 water and wastewater consumption rates and service fees arising from concurrent adoption of the recommended 2013 Toronto Water Operating and Capital Budgets. Consistent with the funding strategy of 9% water rate increases until 2014, adopted by City Council in 2005, it is recommended that the Block 1 and Block 2 rates for all users and flat rate accounts be increased by 9% effective January 1st, 2013. In addition, this report recommends inflationary fee increases for certain water and wastewater services, reflecting cost recovery for these services, and the introduction of two new and four revised sewer related industrial waste surcharge agreement fees.
Background Information
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52183.htm
(November 7, 2012) Presentation from the General Manager, Toronto Water on Toronto Water 2013 Recommended Operating Budget and 2013 – 2022 Recommended Capital Plan 2013 Recommended Water Rate
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52179.pdf
(November 6, 2012) Report with Appendix A from the Acting Deputy City Manager and Chief Financial Officer and the General Manager, Toronto Water on 2013 Water and Wastewater Rates and Service Fees
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52168.pdf
(November 6, 2012) Appendix B
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52165.pdf
(November 6, 2012) Appendix C
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52166.pdf
(November 6, 2012) Appendix D
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52167.pdf
(November 7, 2012) 2013 Staff Recommended Capital Budget - Toronto Water
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52172.pdf
(November 7, 2012) 2013 Staff Recommended Capital Budget - Toronto Water - Appendix 3
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52173.pdf
(November 7, 2012) 2013 Staff Recommended Capital Budget - Toronto Water - Appendix 4
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52174.pdf
(November 7, 2012) 2013 Staff Recommended Capital Budget - Toronto Water - Appendix 5
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52175.pdf
(November 7, 2012) 2013 Toronto Water Capital Budget Briefing Note #1 - Basement Flooding Protection Program - Project List: 2013 to 2017
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52170.pdf
(November 12, 2012) Wrap-Up Notes to Budget Committee - 2013 Recommended Capital Budget Rate Supported Programs
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52182.pdf
(November 7, 2012) 2013 Staff Recommended Operating Budget - Toronto Water
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52176.pdf
(November 7, 2012) 2013 Staff Recommended Operating Budget - Toronto Water - Appendix 3
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52177.pdf
(November 7, 2012) 2013 Staff Recommended Operating Budget - Toronto Water - Appendix 4
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52178.pdf
(November 7, 2012) 2013 Toronto Water Operating Budget Briefing Note #1 - Changes to Industrial Waste Surcharge Program
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52169.pdf
(November 12, 2012) Wrap-Up Notes to Budget Committee - 2013 Recommended Operating Budget Rate Supported Programs
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52181.pdf
(November 2, 2012) Public Notice - 2013 Rate Supported Budgets - Toronto Water and 2013 Water and Wastewater Rates and Service Fees
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52171.pdf
(November 2, 2012) Public Notice - Appendix A
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52163.pdf
(November 2, 2012) Public Notice - Appendix B
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52164.pdf
(November 1, 2012) Report from the Acting Deputy City Manager and Chief Financial Officer and the General Manager, Toronto Water on 2013 Water and Wastewater Rates and Service Fees - Notice of Pending Report
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52162.pdf
(November 19, 2012) Wrap-Up Notes to Executive Committee - 2013 Recommended Capital Budget Rate Supported Programs
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52287.pdf
(November 19, 2012) Wrap-Up Notes to Executive Committee - 2013 Recommended Operating Budget Rate Supported Programs
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-52288.pdf