EY1.5 - 3755 Bloor Street West - Construction Staging Area Time Extension

Decision Type:
ACTION
Status:
Adopted
Ward:
3 - Etobicoke - Lakeshore

Caution: Preliminary decisions, motions, votes and rulings are shown below. Any decisions, motions, votes or rulings should not be considered final until the meeting is complete, and the decisions for this meeting have been confirmed.

Community Council Recommendations

The Etobicoke York Community Council recommends that:

 

1. City Council authorize the continued closure of the east sidewalk and the northbound right-turn lane on Kipling Avenue, between a point 20 metres south of Bloor Street West and a point 62 metres further south, and the provision of a temporary pedestrian walkway within the closed portion of the northbound right-turn lane, from January 1, 2027, to March 31, 2028, inclusive.

 

2. City Council authorize the continued closure of the northbound bicycle lane on the east side of Kipling Avenue, between Bloor Street West and Dundas Street West, from January 1, 2027, to March 31, 2028, inclusive.

 

3. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.

 

4. City Council direct the applicant to continue to cooperate with and provide all necessary assistance to the City engineers, staff and representatives carrying out operation, maintenance, and construction activities to municipal infrastructure within the vicinity of the construction staging area, and at no cost to the City to remove any staging to accommodate the necessary municipal infrastructure work.

 

5. City Council authorize the appropriate City officials to submit directly to the City Council at the appropriate time any necessary Bills to amend the appropriate City of Toronto Municipal Code Chapters to give effect to City Council’s decision, and to reinstate traffic and parking regulations (except with parking rates and hours of operation being consistent to the rates and hours of operation at the time of completion) referred in Recommendations 1 and 2 once the project is complete.

Origin

(November 5, 2026) Report from the Director, Congestion and Network Management, Transportation Services

Summary

As the Toronto Transit Commission (TTC) operates a transit service on Kipling Avenue, City Council approval of this report is required.

 

Multiplex Construction Canada is constructing the new Etobicoke Civic Centre

located at 3755 Bloor Street West. The site is located on the southeast corner of Bloor Street West and Kipling Avenue.

 

By way of background, City Council, at its meeting on June 25 and 26, 2025, approved the subject construction staging area on Kipling Avenue for a period of 6 months, from June 30, 2025, to December 31, 2025. At its subsequent meeting of December 16 and 17, 2025, City Council approved a 12-month extension of the existing construction staging area and associated road occupancy on Kipling Avenue from January 1, 2026, to December 31, 2026.

 

Transportation Services is requesting authorization to extend the duration of the construction staging area on Kipling Avenue for an additional 15 months, from January 1, 2027, to March 31, 2028, to allow for the construction of the development to be completed.

Background Information

(November 5, 2026) Report and Attachment 1 from the Director, Congestion and Network Management, Transportation Services on 3755 Bloor Street West - Construction Staging Area Time Extension
https://www.toronto.ca/legdocs/mmis/2027/ey/bgrd/backgroundfile-290781.pdf

Motions

Motion to Adopt Item moved by Councillor Amber Morley (Carried)