Item - 2026.TE34.119
Tracking Status
- This item was considered by Toronto and East York Community Council on July 8 and 9, 2026 and was adopted without amendment. City Council has delegated authority for this matter to the Toronto and East York Community Council and therefore, the decision is final.
TE34.119 - 65-87 Raglan Avenue - Construction Staging Area Time Extension
- Decision Type:
- ACTION
- Status:
- Adopted
- Schedule Type:
- Delegated
- Ward:
- 12 - Toronto - St. Paul's
Community Council Decision
The Toronto and East York Community Council:
1. Authorized the continuation of the closure of the east sidewalk and a 4.5 metre wide portion of the northbound curb lane on Raglan Avenue, between a point 56.5 metres south of Maplewood Avenue and a point 67 metres further south, from December 1, 2026 to December 31, 2027 inclusive.
2. Continued to rescind the existing parking prohibition in effect from the 1st day of each month to the 15th day of each month, April 1 to November 30 inclusive, on the west side of Raglan Avenue, between a point 47 metres south of Maplewood Avenue and a point 83 metres further south.
3. Continued to rescind the existing maximum one-hour parking in effect from 6:00 a.m. to 6:00 p.m. Monday to Friday from the 16th day to the last day of each month, from April 1 to November 30 inclusive, on the west side of Raglan Avenue, between a point 47 metres south of Maplewood Avenue and a point 83 metres further south.
4. Continued to rescind the existing maximum one-hour parking in effect from 6:00 a.m. to 6:00 p.m. Monday to Friday from December 1 of one year to March 31 of the next following year inclusive, on the west side of Raglan Avenue, between a point 47 metres south of Maplewood Avenue and a point 83 metres further south.
5. Continued to rescind the existing permit parking regulation in effect at all times, except no parking from 7:00 p.m. 1st day to 7:00 p.m. on the 16th day of each month, inclusive, April 1 to December 1, inclusive, from 12:00 midnight to 6:00 a.m. on the even side of Raglan Avenue, between a point 47 metres south of Maplewood Avenue and a point 83 metres further south.
6. Continued to rescind the existing parking prohibition in effect at all times, December 1 to March 31, inclusive, on the east side of Raglan Avenue, between a point 47 metres south of Maplewood Avenue and a point 83 metres further south.
7. Continued to rescind the existing parking prohibition in effect at all times, from the 16th day of each month to the last day of each month, April. 1 to November 30, inclusive, on the east side of Raglan Avenue, between a point 47 metres south of Maplewood Avenue and a point 83 metres further south.
8. Continued to rescind the existing maximum one-hour parking in effect from 6:00 a.m. to 6:00 p.m. Monday to Friday from the 1st day to the 15th day of each month, from Apr. 1 to Nov. 30, inclusive, on the east side of Raglan Avenue, between a point 47 metres south of Maplewood Avenue and a point 83 metres further south.
9. Continued to rescind the existing permit parking regulation in effect at all times, except no parking from 7:00 p.m. on the 16th day of each month to 7:00 p.m. on the 1st day of each month, inclusive, April 1 to December 1, inclusive and no parking anytime from 7:00 p.m. December 1 of one year to 7:00 p.m. April 1 of the next following year, inclusive, from 12:00 midnight to 6:00 a.m. on the odd side of Raglan Avenue, between a point 47 metres south of Maplewood Avenue and a point 83 metres further south.
10. Continued to prohibit stopping at all times on both sides of Raglan Avenue, between a point 47 metres south of Maplewood Avenue and a point 83 metres further south.
11. Continued to authorize a temporary Level 2, Type B -Pedestrian Crossover on Raglan Avenue, at a point 185 metres south of Maplewood Avenue to be in-operation from December 1, 2026, to December 31, 2027, which the issuance of the construction staging permit must be conditional on the Pedestrian Crossover being operational.
12. Directed the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.
13. Directed the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.
14. Directed the applicant to continue to cooperate with and provide all necessary assistance to the City Engineers, staff and representatives carrying out operation, maintenance, and construction activities to municipal infrastructure within the vicinity of the construction staging area, and at no cost to the City to remove any staging to accommodate the necessary municipal infrastructure work.
15. Authorized the appropriate City officials to submit directly to the Toronto and East York Community Council at the appropriate time any necessary Bills to amend the appropriate City of Toronto Municipal Code Chapters to give effect to Toronto and East York Community Council’s decision, and to reinstate traffic and parking regulations (except with parking rates and hours of operation being consistent to the rates and hours of operation at the time of completion) referred in Parts 1 to 11 above, once the project is completed.
Origin
Summary
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision.
Raglan Building Group Inc is constructing a 28-storey residential condominium building at 65-85 Raglan Avenue. The site is located on the east side of Raglan Avenue, between St. Clair Avenue West and Maplewood Avenue.
Toronto and East York Community Council, at its meeting on June 11, 2024, approved the subject construction staging area on Raglan Avenue, from September 1, 2024 to November 30, 2026. The developer is requesting an extension for the construction staging area on Raglan Avenue due to project delays, including challenges with materials and additional unexpected work encountered during construction.
Transportation Services is requesting authorization to extend the duration of the construction staging area on Raglan Avenue for an additional 13 months, from December 1, 2026, to December 31, 2027, to allow for the construction of the development to be completed.
Background Information
https://www.toronto.ca/legdocs/mmis/2026/te/bgrd/backgroundfile-288384.pdf