Item - 2026.TE34.116

Tracking Status

  • This item was considered by Toronto and East York Community Council on July 8 and 9, 2026 and was adopted without amendment. City Council has delegated authority for this matter to the Toronto and East York Community Council and therefore, the decision is final.
  • See also 2026.TE33.40
  • See also By-law 839-2026

TE34.116 - 44 Price Street - Construction Staging Area

Decision Type:
ACTION
Status:
Adopted
Schedule Type:
Delegated
Ward:
11 - University - Rosedale

Community Council Decision

The Toronto and East York Community Council:  

 

1. Authorized the closure of the north boulevard allowance and north sidewalk on Price Street, between a point 48 metres east of Scrivener Square and a point 12.5 metres further east, from May 29, 2026, to October 31, 2027, inclusive.

 

2. Rescinded the existing parking machine regulation in effect from 8:00 a.m. to 9:00 p.m., Monday to Saturday; and 1:00 p.m. to 9:00 p.m. Sunday, at a rate of $4.50 per hour and for a maximum of three hours, on the north side of Price Street, between a point 135 metres east of Yonge Street and a point 12.5 metres further east.

 

3. Prohibited stopping at all times on the north side of Price Street, between a point 135 metres east of Yonge Street and a point 12.5 metres further east.

 

4. Directed the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe.

 

5. Directed the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local Business Improvement Areas and resident associations in advance of any physical road modifications.

 

6. Directed the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public.

 

7. Directed the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, during large scale concrete pours and large-scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public.

 

8. Directed the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

9. Authorized the appropriate City officials to submit directly to Toronto and East York Community Council at the appropriate time any necessary Bills to amend the appropriate City of Toronto Municipal Code Chapters to give effect to Toronto and East York Community Council's direction, and to reinstate the traffic and parking regulations to what they were immediately prior to the date of this revised report (May 21, 2026) from the Director, Congestion and Network Management, Transportation Services once the project is complete.

 

10. Directed that Price Street be returned to its pre-construction traffic and parking regulations (except with parking rates and hours of operation being consistent to the rates and hours of operation at the time of completion) when the project is complete.

Origin

(May 11, 2026) Report from the Director, Congestion and Network Management, Transportation Services

Summary

This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision.

 

Toronto Lawn and Tennis Club Limited is redeveloping the facility at 44 Price Street. The site is located on the north side of Price Street, between Scrivener Square and the east limit of Price Street.

 

Transportation Services is requesting authorization to temporarily close a portion of the north boulevard allowance and the north sidewalk on Price Street, between a point 48 metres east of Scrivener Square and a point 12.5 metres further east for a period of 18 months, from May 29, 2026 to October 31, 2027, in order to facilitate the redevelopment. Pedestrians will be redirected from the north side to the south side of the road.

Background Information

(May 21, 2026) Revised report and Attachment 1 from the Director, Congestion and Network Management, Transportation Services on 44 Price Street - Construction Staging Area
https://www.toronto.ca/legdocs/mmis/2026/te/bgrd/backgroundfile-287586.pdf
(May 11, 2026) Report and Attachment 1 from the Director, Congestion and Network Management, Transportation Services on 44 Price Street - Construction Staging Area

Motions

Motion to Adopt Item moved by Councillor Dianne Saxe (Carried)