TE32.26 - 83-97 River Street and 2-4 Labatt Avenue - Construction Staging Area Time Extension

Decision Type:
ACTION
Status:
Adopted on Consent
Ward:
13 - Toronto Centre

City Council Decision

City Council on May 20 and 21, 2026, adopted the following:

 

1. City Council authorize the continuation of the closure of the east side sidewalk, the easterly northbound cycle track, and the parking layby lane on River Street, between Labatt Avenue and a point 46.5 metres north, and provision of a temporary minimum 2.1 metre wide pedestrian walkway and 1.3 metre wide bike lane within the closed portion of River Street, from May 21, 2026 to December 31, 2029, inclusive.

 

2. City Council authorize the continuation of the closure of the north sidewalk and a 2.2 metre wide portion of the north side eastbound lane on Labatt Avenue, between River Street and a point 40.5 metres east, from May 21, 2026 to December 31, 2029, inclusive.

 

3. City Council authorize the continuation of the full closure of Carfrae Lane, between Labatt Avenue and a point 46.5 metres north, from May 21, 2026 to December 31, 2029, inclusive.

 

4. City Council authorize the continuation of a temporary compulsory stop control for eastbound traffic at the intersection of Labatt Avenue and Defries Street, from May 21, 2026 to December 31, 2029, inclusive.

 

5. City Council rescind the existing parking machine regulation in effect from 10:00 a.m. to 6:00 p.m., Monday to Friday; and 10:00 a.m. to 6:00 p.m. Saturday at a rate of $3.25 per hour and for a maximum of 3 hours, on the east side of River Street, between Labatt Avenue and a point 46.5 metres north.

 

6. City Council rescind the existing permit parking regulation in effect from 12:01 a.m. to 10:00 a.m., at all times on the odd (east) side of River Street, between Labatt Avenue and a point 46.5 metres north.

 

7. City Council prohibit stopping at all times on the east side of River Street, between Labatt Avenue and a point 46.5 metres north.

 

8. City Council rescind the existing parking prohibition on the north side of Labatt Avenue, between River Street and a point 40.5 metres east.

 

9. City Council prohibit stopping at all times on the north side of Labatt Avenue, between River Street and a point 40.5 metres east.

 

10. City Council rescind the existing maximum one hour parking regulation in effect from 8:00 a.m. to 6:00 p.m., Monday to Friday, on the south side of Labatt Avenue, between River Street and a point 40.5 metres east.

 

11. City Council prohibit stopping at all times on the south side of Labatt Avenue, between River Street and a point 40.5 metres east.

 

12. City Council direct the applicant to continue to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe.

 

13. City Council direct the applicant to continue to construct and maintain a fully covered, protected and unobstructed walkway for all pedestrians, including for those with mobility devices, for the entire duration of the construction staging area permit to the satisfaction of the Chief Engineer and Executive Director, Engineering and Construction Services and ensure it is compliant with the Accessibility for Ontarians with Disabilities Act.

 

14. City Council direct the applicant to continue to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night.

 

15. City Council direct the applicant to continue to clearly consult and communicate all construction, parking and road occupancy impacts with local Business Improvement Areas and resident associations in advance of any physical road modifications.

 

16. City Council direct the applicant to continue to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times.

 

17. City Council direct the applicant to continue to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public.

 

18. City Council direct the applicant to continue to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, during large scale concrete pours and large-scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public.

 

19. City Council direct the applicant to continue to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired.

 

20. City Council direct the applicant to continue to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

21. City Council direct the applicant to continue to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.

 

22. City Council direct the applicant, in consultation with Transportation Services, to continue to maintain any bike lanes and install appropriate signage to inform drivers and cyclists of any changes to the cycling lanes.

 

23. City Council authorize the appropriate City officials to submit directly to City Council at the appropriate time any necessary Bills to amend the appropriate City of Toronto Municipal Code Chapters to give effect to City Council's direction, and to reinstate the traffic and parking regulations to what they were immediately prior to the date of the City Council Decision on Item 2022.TE34.115 once the project is complete.

 

24. City Council direct that River Street, Labatt Avenue and Carfrae Lane be returned to its pre-construction traffic and parking regulations (except with parking rates and hours of operation being consistent to the rates and hours of operation at the time of completion) when the project is complete.

 

25. City Council direct the applicant to continue to create a publicly accessible website with regular construction updates and post the website address on the construction site hoarding, which must be prominently place and legible from 20 metres and on all elevations from the construction site.

 

26. City Council direct the applicant to continue to mitigate light pollution by installing a shield/barrier on any lighting standards in close proximity to adjacent residential properties such as cranes.

 

27. City Council in areas where no cycling lanes exist, continue to direct the applicant, in consultation with Transportation Services, to install sharrow markings onto the roadway and display appropriate signage on the hoarding board to inform motorists and cyclist to safely share the road.

 

28. City Council direct the Director, Congestion and Network Management, Transportation Services and the applicant to continue to establish a Construction Management Working Group that meets monthly and invite local stakeholders including Municipal Licensing and Standards, Toronto Buildings, adjacent neighbours, local resident groups, local Business Improvement Areas and local school administration.

 

29. City Council direct the applicant to continue to email monthly construction progress reports to the local Councillor, local residents' association and the Business Improvement Area Board of Management.

Background Information (Community Council)

(April 14, 2026) Report and Attachment 1 from the Director, Congestion and Network Management, Transportation Services on 83-97 River Street and 2-4 Labatt Avenue - Construction Staging Area Time Extension
https://www.toronto.ca/legdocs/mmis/2026/te/bgrd/backgroundfile-286088.pdf

TE32.26 - 83-97 River Street and 2-4 Labatt Avenue - Construction Staging Area Time Extension

Decision Type:
ACTION
Status:
Adopted
Ward:
13 - Toronto Centre

Community Council Recommendations

The Toronto and East York Community Council recommends that:

 

1. City Council authorize the continuation of the closure of the east side sidewalk, the easterly northbound cycle track, and the parking layby lane on River Street, between Labatt Avenue and a point 46.5 metres north, and provision of a temporary minimum 2.1 metre wide pedestrian walkway and 1.3 metre wide bike lane within the closed portion of River Street, from May 21, 2026 to December 31, 2029, inclusive.

 

2. City Council authorize the continuation of the closure of the north sidewalk and a 2.2 metre wide portion of the north side eastbound lane on Labatt Avenue, between River Street and a point 40.5 metres east, from May 21, 2026 to December 31, 2029, inclusive.

 

3. City Council authorize the continuation of the full closure of Carfrae Lane, between Labatt Avenue and a point 46.5 metres north, from May 21, 2026 to December 31, 2029, inclusive.

 

4. City Council authorize the continuation of a temporary compulsory stop control for eastbound traffic at the intersection of Labatt Avenue and Defries Street, from May 21, 2026 to December 31, 2029, inclusive.

 

5. City Council rescind the existing parking machine regulation in effect from 10:00 a.m. to 6:00 p.m., Monday to Friday; and 10:00 a.m. to 6:00 p.m. Saturday at a rate of $3.25 per hour and for a maximum of 3 hours, on the east side of River Street, between Labatt Avenue and a point 46.5 metres north.

 

6. City Council rescind the existing permit parking regulation in effect from 12:01 a.m. to 10:00 a.m., at all times on the odd (east) side of River Street, between Labatt Avenue and a point 46.5 metres north.

 

7. City Council prohibit stopping at all times on the east side of River Street, between Labatt Avenue and a point 46.5 metres north.

 

8. City Council rescind the existing parking prohibition on the north side of Labatt Avenue, between River Street and a point 40.5 metres east.

 

9. City Council prohibit stopping at all times on the north side of Labatt Avenue, between River Street and a point 40.5 metres east.

 

10. City Council rescind the existing maximum one hour parking regulation in effect from 8:00 a.m. to 6:00 p.m., Monday to Friday, on the south side of Labatt Avenue, between River Street and a point 40.5 metres east.

 

11. City Council prohibit stopping at all times on the south side of Labatt Avenue, between River Street and a point 40.5 metres east.

 

12. City Council direct the applicant to continue to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe.

 

13. City Council direct the applicant to continue to construct and maintain a fully covered, protected and unobstructed walkway for all pedestrians, including for those with mobility devices, for the entire duration of the construction staging area permit to the satisfaction of the Chief Engineer and Executive Director, Engineering and Construction Services and ensure it is compliant with the Accessibility for Ontarians with Disabilities Act.

 

14. City Council direct the applicant to continue to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night.

 

15. City Council direct the applicant to continue to clearly consult and communicate all construction, parking and road occupancy impacts with local Business Improvement Areas and resident associations in advance of any physical road modifications.

 

16. City Council direct the applicant to continue to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times.

 

17. City Council direct the applicant to continue to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public.

 

18. City Council direct the applicant to continue to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, during large scale concrete pours and large-scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public.

 

19. City Council direct the applicant to continue to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired.

 

20. City Council direct the applicant to continue to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

21. City Council direct the applicant to continue to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.

 

22. City Council direct the applicant, in consultation with Transportation Services, to continue to maintain any bike lanes and install appropriate signage to inform drivers and cyclists of any changes to the cycling lanes.

 

23. City Council authorize the appropriate City officials to submit directly to City Council at the appropriate time any necessary Bills to amend the appropriate City of Toronto Municipal Code Chapters to give effect to City Council's direction, and to reinstate the traffic and parking regulations to what they were immediately prior to the date of the City Council Decision on Item 2022.TE34.115 once the project is complete.

 

24. City Council direct that River Street, Labatt Avenue and Carfrae Lane be returned to its pre-construction traffic and parking regulations (except with parking rates and hours of operation being consistent to the rates and hours of operation at the time of completion) when the project is complete.

 

25. City Council direct the applicant to continue to create a publicly accessible website with regular construction updates and post the website address on the construction site hoarding, which must be prominently place and legible from 20 metres and on all elevations from the construction site.

 

26. City Council direct the applicant to continue to mitigate light pollution by installing a shield/barrier on any lighting standards in close proximity to adjacent residential properties such as cranes.

 

27. City Council in areas where no cycling lanes exist, continue to direct the applicant, in consultation with Transportation Services, to install sharrow markings onto the roadway and display appropriate signage on the hoarding board to inform motorists and cyclist to safely share the road.

 

28. City Council direct the Director, Congestion and Network Management, Transportation Services and the applicant to continue to establish a Construction Management Working Group that meets monthly and invite local stakeholders including Municipal Licensing and Standards, Toronto Buildings, adjacent neighbours, local resident groups, local Business Improvement Areas and local school administration.

 

29. City Council direct the applicant to continue to email monthly construction progress reports to the local Councillor, local residents' association and the Business Improvement Area Board of Management.

Origin

(April 14, 2026) Report from the Director, Congestion and Network Management, Transportation Services

Summary

As the Toronto Transit Commission (TTC) operates a transit service on River Street, City Council approval of this report is required.

 

Broccolini has undertaken the construction of a 34-storey residential condominium building at 83-97 River Street and 2-4 Labatt Avenue. The site is located on the northeast corner of River Street and Labatt Avenue.

 

By way of background, City Council, at its meeting on July 19, 20, 21 and 22, 2022, adopted Item TE34.115, and in doing so, authorized the temporary closure of the east sidewalk, the northbound bike lane, and the parking lay-by on River Street; the temporary closure of the north sidewalk and a portion of the eastbound lane on Labatt Avenue; and the full closure of a portion of Carfrae Lane, to facilitate construction activities.

 

Construction of the development was paused following the adoption of Item TE34.115 due to market conditions. Subsequently, the development has been repositioned from a condominium building to a purpose‑built rental building, and the applicant is now seeking an extension of the previously authorized closures.

 

In view of the above, Transportation Services is requesting authorization to extend the time duration of the construction staging areas on River Street, Labatt Avenue, and Carfrae Lane for an additional 44 months, from May 21, 2026 to December 31, 2029, to allow for the construction of the development to be completed.

Background Information

(April 14, 2026) Report and Attachment 1 from the Director, Congestion and Network Management, Transportation Services on 83-97 River Street and 2-4 Labatt Avenue - Construction Staging Area Time Extension