Item - 2026.TE31.66
Tracking Status
- This item was considered by Toronto and East York Community Council on April 1, 2026 and was adopted without amendment. City Council has delegated authority for this matter to the Toronto and East York Community Council and therefore, the decision is final.
- See also By-laws 445-2026, 454-2026
TE31.66 - Mirvish Village - Parking and Traffic Amendments (Delegated)
- Decision Type:
- ACTION
- Status:
- Adopted
- Schedule Type:
- Delegated
- Ward:
- 11 - University - Rosedale
Community Council Decision
The Toronto and East York Community Council:
1. Rescinded the existing standing prohibition in effect at all times on both sides of Markham Street, between Bloor Street West and a point 48.8 metres south.
2. Rescinded the existing parking prohibition in effect at all times on the east side of Markham Street, between a point 48.8 metres south of Bloor Street West and Lennox Street.
3. Rescinded the existing parking machine regulation in effect from 8:00 a.m. to 9:00 p.m., Monday to Saturday; 1:00 p.m. to 9:00 p.m. on Sunday, on the west side of Markham Street, between a point 48.8 metres south of Bloor Street West and a point 9 metres north of Lennox Street.
4. Designated Markham Street, between Lennox Street and Bloor Street West, as a one-way for northbound traffic only.
5. Prohibited stopping at all times on the east side of Markham Street, between Lennox Street and Bloor Street West.
6. Prohibited stopping at all times on the west side of Markham Street, between Lennox Street and a point 19 metres north.
7. Designated a passenger loading zone to be in effect at all times, on the west side of Markham Street, between a point 19 metres north of Lennox Street and a point 29 metres further north.
8. Prohibited stopping at all times on the west side of Markham Street, between a point 48 metres north of Lennox Street and a point 56 metres further north.
9. Designated a Delivery Vehicle Parking Zone to be in effect at all times for a maximum period of 10 minutes, on the west side of Markham Street, between a point 104 metres north of Lennox Street and a point 23 metres further north.
10. Prohibited stopping at all times on the west side of Markham Street, between a point 127 metres north of Lennox Street and Bloor Street West.
11. Prohibited westbound left-turns at all times at the intersection of Lennox Street and Markham Street.
12. Rescinded the existing compulsory stop control for southbound traffic on Markham Street at Lennox Street.
Origin
Summary
The Mirvish Village Redevelopment includes properties municipally known as 571-597 Bloor St W, 742-754 and 760-782 Bathurst St, 26-38 Lennox Street, and 581-603 and 588-612 Markham Street with frontage on Bloor Street W, Bathurst Street, Lennox Street, and Markham Street. The owner of the project is Westbank Project Corp, and the corresponding site plan application no 17 187476 STE 19 SA. The proposed mixed-use development includes several mid-rise and tall buildings, ranging from 2 storeys to 27 storeys.
This motion is to implement components of the approved 2021 site plan agreement with Westbank Project Corp.
The development includes public realm improvement consisting of expanding the boulevard on Markham Street by narrowing down the travelled portion of the roadway for a one-way operation. Furthermore, a private east-west driveway under public vehicular easement has been established south of Bloor Street West, between Bathurst Street and Markham Street.
The required parking and traffic amendments on Markham Street, between Lennox Street and Bloor Street West, are as follows:
- This roadway will operate in a one-way northbound direction.
- Stopping will be prohibited at all times on the east side of the street
- On the west side of the street, curbside activities will only be permitted within two constructed lay-bys. A 10-minute delivery zone that will operate at all times is recommended in one lay-by, and a Passenger Loading Zone that will also operate at all times is recommended for the other lay-by.
These traffic and parking amendments will address requirements of the site plan agreement for the newly developed mixed-used development (Mirvish Village) on Markham Street. The amendments will meet new street configurations and operational needs for the corridor. The implementation will accommodate anticipated pedestrian and vehicular volumes while providing a safe environment for all users.
The completion of construction and traffic access on Markham Street is scheduled for the middle of April 2026. As a standard condition of a development site plan approval process, the applicant must contact Transportation Services six months prior to completion for staff to prepare the necessary report to Community Council for by-law approval of traffic and parking amendments. This by-law approval is being expedited because this condition was not included in the site plan application process by Development Review.
Background Information
https://www.toronto.ca/legdocs/mmis/2026/te/bgrd/backgroundfile-285734.pdf
Attachment 1 - Technical Memorandum from the Director, Enforcement and Street Management on Mirvish Village - Parking and Traffic Amendments (Delegated)
https://www.toronto.ca/legdocs/mmis/2026/te/bgrd/backgroundfile-285740.pdf