Item - 2026.IE28.2

Tracking Status

  • City Council adopted this item on April 22 and 23, 2026 without amendments.
  • This item was considered by the Infrastructure and Environment Committee on April 7, 2026 and adopted without amendment. It will be considered by City Council on April 22 and 23, 2026.

IE28.2 - Redesign Study of the Intersection of Eglinton Avenue West and the Allen Road Expressway - April 2026 Update

Decision Type:
ACTION
Status:
Adopted
Wards:
8 - Eglinton - Lawrence, 12 - Toronto - St. Paul's

City Council Decision

City Council on April 22 and 23, 2026, adopted the following:

 

1. City Council receive the report (March 20, 2026) from the General Manager, Transportation Services for information.

Background Information (Committee)

(March 20, 2026) Report from the General Manager, Transportation Services on Redesign Study of the Intersection of Eglinton Avenue West and the Allen Road Expressway - April 2026 Update
https://www.toronto.ca/legdocs/mmis/2026/ie/bgrd/backgroundfile-285427.pdf

Communications (Committee)

(April 1, 2026) E-mail from Adam Rodgers (IE.Supp)
(April 2, 2026) E-mail from Elio Kaakee (IE.Supp)
(April 7, 2026) E-mail from Nicole Corrado (IE.New)

Communications (City Council)

(April 7, 2026) Submission from Michael Longfield, CycleTO (CC.Main)
https://www.toronto.ca/legdocs/mmis/2026/cc/comm/communicationfile-209595.pdf

Motions (City Council)

Motion to Adopt Item (Carried)

IE28.2 - Redesign Study of the Intersection of Eglinton Avenue West and the Allen Road Expressway - April 2026 Update

Decision Type:
ACTION
Status:
Adopted
Wards:
8 - Eglinton - Lawrence, 12 - Toronto - St. Paul's

Committee Recommendations

The Infrastructure and Environment Committee recommends that:

 

1. City Council receive the report (March 20, 2026) from the General Manager, Transportation Services, for information.

Origin

(March 20, 2026) Report from the General Manager, Transportation Services

Summary

Since the opening of the newly designed Eglinton Avenue West and Allen Road expressway intersection in 2023, traffic capacity issues at the intersection have caused traffic congestion along Eglinton Avenue West. With many neighbourhood streets being used as short-cuts to Allen Road, traffic congestion is also significantly impacting neighbourhood streets.

 

On February 5, 2025, City Council directed the General Manager, Transportation Services, to initiate a study to examine redesign options to improve the operation of the Eglinton Avenue West and Allen Road intersection, and to report to the Infrastructure and Environment Committee in the first quarter of 2026 with a progress update and recommended workplan.

 

This report includes:

 

-  An update on the status and work plan of the Eglinton and Allen Intersection Study as per Council request; and

 

-  A summary of the recent monitoring results following the traffic pattern changes implemented in December 2025 to reduce infiltration on local streets in the neighbourhood.

Background Information

(March 20, 2026) Report from the General Manager, Transportation Services on Redesign Study of the Intersection of Eglinton Avenue West and the Allen Road Expressway - April 2026 Update
https://www.toronto.ca/legdocs/mmis/2026/ie/bgrd/backgroundfile-285427.pdf

Communications

(April 1, 2026) E-mail from Adam Rodgers (IE.Supp)
(April 2, 2026) E-mail from Elio Kaakee (IE.Supp)
(April 7, 2026) E-mail from Nicole Corrado (IE.New)

Speakers

Adam Rodgers

Motions

Motion to Adopt Item moved by Councillor Mike Colle (Carried)
Source: Toronto City Clerk at www.toronto.ca/council