TTC6.14 - Provincial LRT Program - Line 5 Eglinton Update
- Decision Type:
- ACTION
- Status:
- Adopted
Confidential Attachment - This report contains information explicitly supplied in confidence to the City or local board by Canada, a province or territory or a Crown agency of any of them.
Commission Decision
The TTC Board:
1. Received this report for information.
2. Authorized that the information contained in Confidential Attachment 1 remain confidential, as it contains information supplied in confidence to the TTC by a Crown agency, Metrolinx.
Origin
Summary
The TTC, Metrolinx and Crosslinx Transit Solution continue to work together to get Line 5 ready for revenue service. On June 16, 2025, train operations were transferred into the TTC’s Transit Control Centre from a temporary control centre as testing, training and construction continue. There are, however, still more phases and milestones to be safely completed before final handover to the TTC occurs.
Handover comes only after substantial completion is achieved, which requires that the Project's Independent Certifier has certified that CTS has demonstrated the successful delivery of Line 5 in accordance with the requirements set out in its Project Agreement.
Background Information
https://www.toronto.ca/legdocs/mmis/2025/ttc/bgrd/backgroundfile-256530.pdf
Attachment 1 - Confidential Information
Communications
https://www.toronto.ca/legdocs/mmis/2025/ttc/comm/communicationfile-193597.pdf