TTC1.7 - Making Old Mill Station Accessible

Decision Type:
ACTION
Status:
Adopted

Confidential Attachment - This report contains information about a position, plan, procedure, criteria or instruction to be applied to any negotiations carried on or to be carried on by or on behalf of the City or local board.

Commission Decision

The TTC Board:

 

1. Authorized the award of Contract W45-8, Old Mill Station – Easier Access III to Maystar General Contractors Inc. in the amount of $25,690,748.88, inclusive of all taxes, on the basis of the lowest-priced acceptable bid.

 

2. Approved a reallocation of $8.5 million of permanent savings from the SRT Life Extension project and increase the total project cost for the Easier Access III program to fund the Contract award.


3. Subject to recommendation 2 above, authorized the recommended budget adjustments to the TTC’s 2025-2034 Capital Budget and Plan to be included in the TTC’s Capital Variance Report submission to the City of Toronto for the four months ended April 30, 2025, for City Council consideration and approval.

 

4. Approved the recommendation contained in the Confidential Attachment 1 and authorized that the information in the Confidential Attachment remains confidential as it contains information about a position, plan, procedure, criteria or instruction to be applied to any negotiations carried on or to be carried on by or on behalf of the City or local board.

Origin

(January 27, 2025) Report from the Chief Capital Officer

Summary

The purpose of this report is to obtain authorization for the award of Contract W45-8, Old Mill Station Easier Access III (EAIII), to Maystar General Contractors Inc. in the amount of $25,690,748.88, inclusive of all taxes, on the basis of the lowest-priced acceptable bid.

 

The contract work provides services for the construction of two elevators at Old Mill Station from street level to each side platform, new tactile attention tiles, station power upgrade, associated signage, mechanical and electrical upgrades and other associated elements to provide a barrier-free path throughout the station.

 

The construction phase of the contract is scheduled to commence in Q2 2025.

Background Information

(January 27, 2025) Revised Report and Appendix A and B from the Chief Capital Officer on Making Old Mill Station Accessible (January 22, 2025)
https://www.toronto.ca/legdocs/mmis/2025/ttc/bgrd/backgroundfile-252232.pdf
Confidential Attachment 1

Motions

Motion to Adopt Item moved by Fenton Jagdeo (Carried)