TE25.36 - 60 Queen Street East - Construction Staging Area Time Extension

Decision Type:
ACTION
Status:
Amended
Schedule Type:
Delegated
Ward:
13 - Toronto Centre

Community Council Decision

The Toronto and East York Community Council:

 

1. Authorized the closure of the west sidewalk and a 5.5 metre wide portion of the southbound on Dalhousie Street, between Queen Street East and a point 33 metres north, from September 19, 2025 to February 31, 2027, inclusive.

 

2. Directed the applicant to continue to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe.

 

3. Directed the applicant to continue to construct and maintain a fully covered, protected and unobstructed walkway for all pedestrians, including for those with mobility devices, for the entire duration of the construction staging area permit to the satisfaction of the Chief Engineer and Executive Director, Engineering and Construction Services and ensure it is compliant with the Accessibility for Ontarians with Disabilities Act.

 

4. Directed the applicant to continue to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night.

 

5. Directed the applicant to continue to clearly consult and communicate all construction, parking and road occupancy impacts with local Business Improvement Areas and resident associations in advance of any physical road modifications.

 

6. Directed the applicant to continue to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times.

 

7. Directed the applicant to continue to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public.

 

8. Directed the applicant to continue to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, during large scale concrete pours and large-scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public.

 

9. Directed the applicant to continue to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired.

 

10. Directed the applicant to continue to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

11. Directed the applicant to continue to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.

 

12. Directed the applicant, in consultation with Transportation Services, to continue to maintain any bike lanes, and install appropriate signage to inform drivers and cyclists of any changes to the cycling lanes.

 

13. Directed that Dalhousie Street be returned to its pre-construction traffic and parking regulations when the project is complete.

 

14. Directed that the occupation permit for construction staging on Dalhousie Street continue to be conditional, subject to there being no conflicts with Metrolinx transit project construction.

 

15. Directed the applicant to continue to create a publicly accessible website with regular construction updates and post the website address on the construction site hoarding, which must be prominently place and legible from 20 metres and on all elevations from the construction site.

 

16. Directed the applicant to continue to mitigate light pollution by installing a shield/barrier on any lighting standards in close proximity to adjacent residential properties such as cranes.

 

17. In areas where no cycling lanes exist, continue to direct the applicant, in consultation with Transportation Services, to install sharrow markings onto the roadway and display appropriate signage on the hoarding board to inform motorists and cyclist to safely share the road.

 

18. Directed the Director, Traffic Management, Transportation Services and the applicant to continue to establish a Construction Management Working Group that meets monthly and invite local stakeholders including Municipal Licensing and Standards, Toronto Buildings, adjacent neighbours, local resident groups, local Business Improvement Areas and local school administration.

 

19. Directed the applicant to continue to email monthly construction progress reports to the local Councillor, local residents' association and the Business Improvement Area Board of Management.

Origin

(September 2, 2025) Report from Director, Traffic Management, Transportation Services

Summary

This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision.

 

Deltera Inc. has undertaken the construction of a 57-storey mixed use building at 60 Queen Street East. The site is located on the northwest corner of Queen Street East and Dalhousie Street.

 

At its meeting of November 15, 2023, Toronto and East York Community Council authorized the temporary closure of the west sidewalk and a 4.2 metre wide portion of the southbound lane on Dalhousie Street, from November 16, 2023 to December 31, 2024, to facilitate construction staging operations.

 

At the time of this report, the below grade construction is underway. The next phase of construction will require a larger footprint to accommodate a material hoist and additional equipment. As a result, the occupation on the west curb lane on Dalhousie Street will increase from 4.2 metres to 5.5 metres. Pedestrian movements on the west sidewalk will continue to be restricted. The appropriate sidewalk closure signage is installed to inform pedestrians to cross to the other side of the roadway.

 

Transportation Services is requesting authorization to extend the time duration of the construction staging area on Dalhousie Street for an additional 37 months, from September 19, 2025, to September 30, 2028, to allow for the construction of the development to be completed.

Background Information

(September 2, 2025) Report and Attachment 1 from the Director, Traffic Management, Transportation Services on 60 Queen Street East - Construction Staging Area Time Extension
https://www.toronto.ca/legdocs/mmis/2025/te/bgrd/backgroundfile-258150.pdf

Motions

1 - Motion to Amend Item moved by Councillor Chris Moise (Carried)

That:

 

1. Toronto and East York Community Council delete Recommendation 1:

 

Recommendation to be deleted:

 

1. Toronto and East York Community Council authorize the closure of the west sidewalk and a 5.5 metre wide portion of the southbound on Dalhousie Street, between Queen Street East and a point 33 metres north, from September 19, 2025 to September 30, 2028, inclusive, to allow for the completion of the development.

 

and adopt instead the following:

 

1. Toronto and East York Community Council authorize the closure of the west sidewalk and a 5.5 metre wide portion of the southbound on Dalhousie Street, between Queen Street East and a point 33 metres north, from September 19, 2025 to February 31, 2027, inclusive.


Motion to Adopt Item as Amended moved by Councillor Chris Moise (Carried)