TE21.26 - 1 Roxborough Street West - Construction Staging Area

Decision Type:
ACTION
Status:
Adopted
Schedule Type:
Delegated
Ward:
11 - University - Rosedale

Community Council Decision

The Toronto and East York Community Council:

 

1. Authorized a full closure of Paul Hahn Lane, between Roxborough Street West and a point 49 metres south, from April 30, 2025 to November 30, 2025.

 

2. Rescinded the existing parking machine regulation in effect from 10:00 a.m. to 9:00 p.m.; Monday to Saturday; 1:00 p.m. to 9:00 p.m. Sunday, at a rate of $4.25 per hour for maximum period of 3 hours, on both sides of Roxborough Street West between Yonge Street and a point 33 metres west.

 

3. Rescinded the existing maximum 1 hour parking regulation in effect from 10:00 a.m. to 6:00 p.m., on the north side of Roxborough Street West, between Yonge Street and a point 33 metres west.

 

4. Rescinded the existing maximum 1 hour parking regulation in effect from 10:00 a.m. to 6:00 p.m., on the south side of Roxborough Street West, between Yonge Street and a point 56 metres west.

 

5. Rescinded the existing permit parking regulation in effect from 12:01a.m. to 10:00 a.m., on the even (north) side of Roxborough Street West, from Yonge Street to a point 33 metres west.

 

6. Rescinded the existing permit parking regulation in effect from 12:01 a.m. to 10:00 a.m., on the odd (south) side of Roxborough Street West, from Yonge Street to a point 56 metres west.

 

7. Prohibited stopping at all times on the north side of Roxborough Street West, between Yonge Street and a point 33 metres west.

 

8. Prohibited stopping at all times on the south side of Roxborough Street West, between Yonge Street and a point 56 metres west.

 

9. Directed the applicant to sweep the construction site, adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe.

 

10. Directed the applicant to construct and maintain a fully covered, protected and unobstructed walkway for all pedestrians, including for those with mobility devices, for the entire duration of the construction staging area permit to the satisfaction of the Chief Engineer and Executive Director, Engineering and Construction Services and ensure it is compliant with the Accessibility for Ontarians with Disabilities Act.

 

11. Directed the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night.

 

12. Directed the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local Business Improvement Areas and resident associations in advance of any physical road modifications.

 

13. Directed the applicant to install appropriate signage and request the applicant to maintain all sightlines to ensure that pedestrians, cyclists and motorists safety is considered at all times.

 

14. Directed the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public.

 

15. Directed the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public.

 

16. Directed the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired.

 

17. Directed the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

18. Directed the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.

 

19. Directed the applicant to cooperate with and provide all necessary assistance to the City Engineers, staff and representatives carrying out operation, maintenance and construction activities to municipal infrastructure within the vicinity of the construction staging area, and at no cost to the City to remove any staging to accommodate the necessary municipal infrastructure work.

 

20. Directed that Roxborough Street West and Paul Hahn Lane be returned to its pre-construction traffic and parking regulations when the project is complete.

 

21. Directed the applicant to provide monthly community meetings to discuss any concerns raised by the community.

Origin

(March 18, 2025) Report from the Director, Traffic Management, Transportation Services

Summary

This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision.

 

North Drive is constructing a 12-storey residential condominium building at 1 Roxborough Street West. The site is located on the southwest corner of Yonge Street and Roxborough Street West.

 

The project will be undertaken in multiple phases, with varying degrees of sidewalk and traffic lane closures on Roxborough Street West, as well as a full closure of Paul Hahn Lane. Phase 1 of the project will require a full closure of Paul Hahn Lane, between Roxborough Street West and a point 49 metres south for a period of 7 months, to facilitate excavation and shorting activities. In addition, a stopping prohibition will be implemented on the south side of Roxborough Street West to ensure safe inbound and outbound movements from access/egress points on the south side of Roxborough Street.

 

It should be noted that the approval of the construction staging permit is conditional on all construction vehicles following the designated haul route plan. Construction vehicles may only access on the construction gate on the south side of Roxborough Street West from Yonge Street.  Likewise, when egressing the site, construction vehicles may only travel eastbound to Yonge Street. Construction vehicles are prohibited from travelling westbound on Roxborough Street West to Avenue Road. It is the obligation of the developer to ensure that access into the site or egress movements out of the site are conducted safely.

Background Information

(March 26, 2025) Revised report and Attachment 1 from the Director, Traffic Management, Transportation Services on 1 Roxborough Street West - Construction Staging Area
https://www.toronto.ca/legdocs/mmis/2025/te/bgrd/backgroundfile-254075.pdf
(March 18, 2025) Report and Attachment 1 from the Director, Traffic Management, Transportation Services on 1 Roxborough Street West - Construction Staging Area
https://www.toronto.ca/legdocs/mmis/2025/te/bgrd/backgroundfile-253897.pdf

Communications

(April 1, 2025) Letter from John Caliendo and Ian Carmichael, Co-Chairs, ABC Residents Association (TE.Supp)
https://www.toronto.ca/legdocs/mmis/2025/te/comm/communicationfile-188902.pdf
(April 2, 2025) Letter from Holly Reid and Tom Worrall on behalf of Yonge4All (TE.Supp)
https://www.toronto.ca/legdocs/mmis/2025/te/comm/communicationfile-188906.pdf

Speakers

Mary Helen Spence, ABC Residents Association

Motions

Motion to Adopt Item moved by Councillor Dianne Saxe (Carried)