Item - 2025.TE20.28
Tracking Status
- This item was considered by Toronto and East York Community Council on February 20, 2025 and was adopted without amendment. City Council has delegated authority for this matter to the Toronto and East York Community Council and therefore, the decision is final.
TE20.28 - 176-178 Front Street East and 33 Sherbourne Street - Construction Staging Area Time Extension
- Decision Type:
- ACTION
- Status:
- Adopted
- Schedule Type:
- Delegated
- Ward:
- 13 - Toronto Centre
Community Council Decision
The Toronto and East York Community Council:
1. Authorized the continuation of the closure of the north sidewalk and a 2.2 metre wide portion of the westbound curb lane on Front Street East, between Sherbourne Street and a point 58 metres east, and provision of a temporary pedestrian walkway within the closed portion of Front Street East, from February 21, 2025 to September 30, 2025 inclusive.
2. Directed the applicant to continue to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe.
3. Directed the applicant to continue to construct and maintain a fully covered, protected and unobstructed walkway for all pedestrians, including for those with mobility devices, for the entire duration of the construction staging area permit to the satisfaction of the Chief Engineer and Executive Director, Engineering and Construction Services and ensure it is compliant with the Accessibility for Ontarians with Disabilities Act.
4. Directed the applicant to continue to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night.
5. Directed the applicant to continue to clearly consult and communicate all construction, parking and road occupancy impacts with local Business Improvement Areas and resident associations in advance of any physical road modifications.
6. Directed the applicant to continue to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists, and motorists' safety is considered at all times.
7. Directed the applicant to continue to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public.
8. Directed the applicant to continue to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public.
9. Directed the applicant to continue to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired.
10. Directed the applicant to continue to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.
11. Directed the applicant to continue to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.
12. Directed the applicant, in consultation with Transportation Services, to continue to maintain any bike lanes, and install appropriate signage to inform drivers and cyclists of any changes to the cycling lanes.
13. Directed that the occupation permit for construction staging on Front Street East continue to be conditional, subject to there being no conflicts with Metrolinx transit project construction.
14. Directed the applicant to continue to create a publicly accessible website with regular construction updates and post the website address on the construction site hoarding, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.
15. Directed the applicant to continue to mitigate light pollution by installing a shield/barrier on any lighting standards within close proximity to adjacent residential properties, such as cranes.
16. In areas where no cycling lanes exist, directed the applicant to continue to consult with Transportation Services to install sharrow markings onto the roadway and display appropriate signage on the hoarding board to inform motorists and cyclists to safely share the road.
17. Directed the Director, Traffic Management, Transportation Services and the applicant to continue to establish a Construction Management Working Group that meets monthly and invite local stakeholders including Municipal Licensing and Standards, Toronto Building, adjacent neighbours, local resident groups, local Business Improvement Areas, and local school administration.
18. Directed the applicant to continue to email monthly construction progress reports to the local Councillor, residents' association and Business Improvement Area Board of Management.
19. Directed that Front Street East be returned to its pre-construction traffic and parking regulations when the project is complete.
Origin
Summary
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision.
Menkes Developments Ltd. has undertaken the construction of a 39-storey residential condominium building at 180 Front Street East (formerly 176-178 Front Street East and 33 Sherbourne Street). The site is located at the northeast corner of Front Street East and Sherbourne Street.
At its meeting of November 15, 2023, Toronto and East York Community Council authorized the temporary closure of the east sidewalk and a portion of the northbound curb lane on Front Street East, between Sherbourne Street and a point 58 metres east, from November 16, 2023 to December 31, 2024. At the time, the developer indicated they would require the staging area for a total of 26 months, from November 16, 2023 to December 31, 2025, however, the occupation was only approved for a 14 month period.
Transportation Services is requesting authorization to extend the duration of the construction staging area on Front Street East for an additional eight months, from February 21, 2025 to September 30, 2025, to allow for the construction of the development to be completed.
Background Information
https://www.toronto.ca/legdocs/mmis/2025/te/bgrd/backgroundfile-253194.pdf
(January 31, 2025) Report and Attachment 1 from the Director, Traffic Management, Transportation Services on 176-178 Front Street East and 33 Sherbourne Street - Construction Staging Area Time Extension
https://www.toronto.ca/legdocs/mmis/2025/te/bgrd/backgroundfile-252992.pdf