NY26.25 - 109 Erskine Avenue - Construction Staging Area Time Extension
- Decision Type:
- ACTION
- Status:
- Adopted
- Schedule Type:
- Delegated
- Ward:
- 15 - Don Valley West
Community Council Decision
North York Community Council:
1. Authorized the continuation of the closure of the south sidewalk and a 2.4-metre-wide portion of the eastbound curb lane on Erskine Avenue, between a point 27 metres west of Redpath Avenue and a point 30 metres further west, and a provision of a temporary pedestrian walkway within the closed portion of the eastbound curb lane, from October 1, 2025 to February 28, 2026, inclusive.
2. Directed the applicant to continue to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed and to be cleared of any construction debris and made safe.
3. Directed the applicant to continue to construct and maintain a fully covered, protected and unobstructed walkway for all pedestrians, including for those with mobility devices, for the entire duration of the construction staging area permit to the satisfaction of the City engineer and ensure it is compliant with the Accessibility for Ontarians with Disabilities Act (AODA).
4. Directed the applicant to continue to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night.
5. Directed the applicant to continue to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications.
6. Directed the applicant to continue to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times.
7. Directed the applicant to continue to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public.
8. Directed the applicant to continue to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, during large-scale concrete pours and material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public.
9. Directed the applicant to continue to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired.
10. Directed the applicant to continue to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.
11. Directed the applicant to continue to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.
12. Directed the applicant to continue to cooperate with and provide all necessary assistance to the City Engineers, staff and representatives carrying out operation, maintenance, and construction activities to municipal infrastructure with the vicinity of the construction staging area, and at no cost to the City to remove any staging to accommodate the necessary municipal infrastructure work.
13. Directed the applicant to continue to provide monthly community meetings, to discuss any concerns raised by the community.
14. Directed that Erskine Avenue be returned to its pre-construction traffic and parking regulations when the project is complete.
Origin
Summary
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision.
LCG Residential Builders Ltd., has undertaken the construction of a 22-storey residential building at 109 Erskine Avenue. The site is located on the south side of Erskine Avenue, approximately 350 metres east of Yonge Street.
At its meeting of December 3, 2024, North York Community Council authorized the temporary closure of the eastbound curb lane and the south sidewalk on Erskine Avenue from December 4, 2024 to September 30, 2025. At the time, the developer indicated they would require the staging area for a total of 17 months, from December 4, 2024 to April 30, 2026, however, the occupation was only approved for a 10 month period.
Transportation Services is requesting authorization to extend the time duration of the construction staging area on Erskine Avenue for an additional five months, from October 1, 2025 to February 28, 2026, to allow for the construction of the development to be completed.