Item - 2025.NY25.23
Tracking Status
- This item was considered by North York Community Council on July 3, 2025 and was adopted with amendments. City Council has delegated authority for this matter to the North York Community Council and therefore, the decision is final.
- See also By-law 666-2025
NY25.23 - 25 St. Dennis Drive - Construction Staging Area
- Decision Type:
- ACTION
- Status:
- Amended
- Schedule Type:
- Delegated
- Ward:
- 16 - Don Valley East
Community Council Decision
North York Community Council:
1. Authorized the closure of the southerly eastbound designated bike lane and a 4.5 metre wide portion of the eastbound curb lane on St. Dennis Drive, between a point 77 metres west of Deauville Lane and a point 125 metres further west, from September 1, 2025 to December 31, 2026 inclusive.
2. Prohibited stopping at all times on the north side of St. Dennis Drive, between a point 65 metres west of Deauville Lane and a point 65 metres further west.
3. Directed the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe.
4. Directed the applicant to construct and maintain a fully covered, protected and unobstructed walkway for all pedestrians, including for those with mobility devices, for the entire duration of the construction staging area permit to the satisfaction of the City engineer and ensure it is compliant with the Accessibility for Ontarians with Disabilities Act (AODA).
5. Directed the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night.
6. Directed the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications.
7. Directed the applicant to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists, and motorists' safety is considered at all times.
8. Directed the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public.
9. Directed the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public.
10. Directed the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired.
11. Directed the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.
12. Directed the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.
13. Directed the applicant, in consultation with Transportation Services, to maintain any bicycle lanes, and install appropriate signage to inform drivers and cyclists of any changes to the bicycle lanes.
14. Directed the applicant to cooperate with and provide all necessary assistance to the City Engineers, staff and representatives carrying out operation, maintenance, and construction activities to municipal infrastructure with the vicinity of the construction staging area, and at no cost to the City to remove any staging to accommodate the necessary municipal infrastructure work.
15. Directed that the occupation permit for construction staging on St. Dennis Drive be conditional, subject to there being no conflicts with Metrolinx transit project construction.
16. Directed that St. Dennis Drive be returned to its pre-construction traffic and parking regulations when the project is complete.
Origin
Summary
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision.
25 St Dennis LP is constructing a 12-storey condominium at 25 St. Dennis Drive. The site is located on the south side of St. Dennis Drive, between Don Mills Road and Deauville Lane.
Transportation Services is requesting authorization to temporarily close a portion of the eastbound curb lane and eastbound cycle track on St. Dennis Drive for a period of 16 months, from September 1, 2025 to December 31, 2026, in order to enable construction of the above-mentioned development. Pedestrian movements will be maintained in a covered and protected walkway within the existing sidewalk on the south side.
Background Information
https://www.toronto.ca/legdocs/mmis/2025/ny/bgrd/backgroundfile-256503.pdf
Motions
That North York Community Council:
1. Delete Recommendation 1 in the report (June 16, 2025) from the Director, Traffic Management, Transportation Services,
Recommendation to be deleted
1. North York Community Council authorize the closure of the southerly eastbound designated bike lane and a 4.5 metre wide portion of the eastbound curb lane on St. Dennis Drive, between Deauville Lane and a point 77 metres west, from September 1, 2025 to December 31, 2026 inclusive.
and replace it with the following recommendation:
1. North York Community Council authorize the closure of the southerly eastbound designated bike lane and a 4.5 metre wide portion of the eastbound curb lane on St. Dennis Drive, between a point 77 metres west of Deauville Lane and a point 125 metres further west, from September 1, 2025 to December 31, 2026 inclusive.