IE23.11 - Hesketh Court - Proposed New Sidewalk Construction

Decision Type:
ACTION
Status:
Adopted on Consent
Ward:
16 - Don Valley East

City Council Decision

City Council on July 23 and 24, 2025, adopted the following:

 

1. City Council direct the Chief Engineer and Executive Director, Engineering and Construction Services and the General Manager, Transportation Services, to remove the proposed new sidewalk construction project on Hesketh Court from the 26ECS-RD-02RR contract for local road resurfacing.

Background Information (Committee)

(June 25, 2025) Letter from Councillor Jon Burnside on Hesketh Court and Tinder Crescent - Proposed New Sidewalk Construction
https://www.toronto.ca/legdocs/mmis/2025/ie/bgrd/backgroundfile-256770.pdf

Communications (Committee)

(July 3, 2025) E-mail from George Bell (IE.Supp)
(July 8, 2025) Letter from Susan Bakshi, Walk Toronto (IE.Supp)
https://www.toronto.ca/legdocs/mmis/2025/ie/comm/communicationfile-194385.pdf
(July 10, 2025) Letter from Eddy Ionescu (IE.Supp)
(July 10, 2025) E-mail from Nicole Corrado (IE.Supp)
(July 10, 2025) E-mail from Eddy Ionescu (IE.Supp)

IE23.11 - Hesketh Court - Proposed New Sidewalk Construction

Decision Type:
ACTION
Status:
Amended
Ward:
16 - Don Valley East

Committee Recommendations

The Infrastructure and Environment Committee recommends that:

 

1. City Council direct the Chief Engineer and Executive Director, Engineering and Construction Services and the General Manager, Transportation Services, to remove the proposed new sidewalk construction project on Hesketh Court from the 26ECS-RD-02RR contract for local road resurfacing.

Origin

(June 25, 2025) Letter from Councillor Jon Burnside

Summary

This motion aims to amend the plans for project 26ECS-RD-02RR which outlines a local road resurfacing along with the construction of sidewalks on Hesketh Court and Tinder Crescent.

 

Tinder Crescent and Hesketh Court are local roads within the Victoria Village neighborhood of Ward 16. These roads serve residents who live there as they do not provide through access; therefore traffic is highly local. Transportation plans to reconstruct Hesketh and Tinder with a sidewalk in 2026-2027. Residents were not formally notified of the project but were informed by a staff member taking measurements of the road.

 

Numerous residents objected to the sidewalk construction project which prompted my office to conduct a survey to receive feedback from the community on both roads. For Hesketh Court, 85 percent of residents were against the sidewalk project (29/34). On Tinder Crescent, 76 percent of residents were against (10/13). The request from the community is clear, on behalf of these residents I request the project be amended to not include the proposed sidewalk component but continue with road resurfacing on both roads.

Background Information

(June 25, 2025) Letter from Councillor Jon Burnside on Hesketh Court and Tinder Crescent - Proposed New Sidewalk Construction
https://www.toronto.ca/legdocs/mmis/2025/ie/bgrd/backgroundfile-256770.pdf

Communications

(July 3, 2025) E-mail from George Bell (IE.Supp)
(July 8, 2025) Letter from Susan Bakshi, Walk Toronto (IE.Supp)
https://www.toronto.ca/legdocs/mmis/2025/ie/comm/communicationfile-194385.pdf
(July 10, 2025) Letter from Eddy Ionescu (IE.Supp)
(July 10, 2025) E-mail from Nicole Corrado (IE.Supp)
(July 10, 2025) E-mail from Eddy Ionescu (IE.Supp)

Speakers

Adam Roy Cohoon

Motions

Motion to Amend Item moved by Councillor Paula Fletcher (Final)

Infrastructure and Environment Committee:

 

1. Delete the words "and Tinder Crescent" so the recommendation now reads as follows:

 

1. The Infrastructure and Environment Committee recommend that City Council direct the Chief Engineer and Executive Director, Engineering and Construction Services and the General Manager, Transportation Services, to remove the proposed new sidewalk construction projects on Hesketh Court and Tinder Crescent from the 26ECS-RD-02RR contract for local road resurfacing.

Source: Toronto City Clerk at www.toronto.ca/council