Item - 2025.IE21.11
Tracking Status
- City Council adopted this item on May 21 and 22, 2025 without amendments and without debate.
- This item was considered by the Infrastructure and Environment Committee on May 7, 2025 and adopted without amendment. It will be considered by City Council on May 21 and 22, 2025.
IE21.11 - Watermain Replacement and Sidewalk Construction on York Downs Drive from Bathurst Street to Sandringham Drive - Amendment to the Plans for Construction Project 25ECS-LU-02SU
- Decision Type:
- ACTION
- Status:
- Adopted on Consent
- Ward:
- 6 - York Centre
City Council Decision
City Council on May 21 and 22, 2025, adopted the following:
1. City Council direct the Chief Engineer and Executive Director, Engineering and Construction Services and the General Manager, Transportation Services, to remove the proposed new sidewalk construction project on York Downs Drive from the 25ECS-LU-02SU contract for local road resurfacing and watermain replacement on York Downs Drive.
Background Information (Committee)
https://www.toronto.ca/legdocs/mmis/2025/ie/bgrd/backgroundfile-255204.pdf
IE21.11 - Watermain Replacement and Sidewalk Construction on York Downs Drive from Bathurst Street to Sandringham Drive - Amendment to the Plans for Construction Project 25ECS-LU-02SU
- Decision Type:
- ACTION
- Status:
- Adopted
- Ward:
- 6 - York Centre
Committee Recommendations
The Infrastructure and Environment Committee recommends that:
1. City Council direct the Chief Engineer and Executive Director, Engineering and Construction Services and the General Manager, Transportation Services, to remove the proposed new sidewalk construction project on York Downs Drive from the 25ECS-LU-02SU contract for local road resurfacing and watermain replacement on York Downs Drive.
Origin
Summary
This motion seeks to amend the plans for construction project 25ECS-LU-02SU - Watermain Replacement and Sidewalk Construction on York Downs Drive from Bathurst Street to Sandringham Drive.
In late June 2025, the City is planning to undertake sidewalk construction and watermain replacements on York Downs Drive from Raeburn Avenue to Armour Boulevard. Notices of this project were distributed to those who are impacted. The sidewalk portion of this project is divided into two components with planned installations on the north side of York Downs Drive between Armour Boulevard and Elderberry Court, and another sidewalk being installed along the south side of the street between Elderberry Court and the cul-de-sac.
After some objections, we distributed surveys to gauge feedback from residents, and most expressed that they are against the plans for the sidewalk installation component.19 out of 20 residents stated their strong opposition towards having sidewalks installed on these streets. Therefore, we request that this project be revised to discard the proposed sidewalk component but continue with the remainder of the construction plan.
Background Information
https://www.toronto.ca/legdocs/mmis/2025/ie/bgrd/backgroundfile-255204.pdf