Item - 2025.EX25.7
Tracking Status
- City Council adopted this item on July 23 and 24, 2025 without amendments and without debate.
- This item was considered by the Executive Committee on July 16, 2025 and adopted without amendment. It will be considered by City Council on July 23 and 24, 2025.
EX25.7 - Capital Variance Report for the Twelve Months Ended December 31, 2024
- Decision Type:
- ACTION
- Status:
- Adopted on Consent
- Wards:
- All
City Council Decision
City Council on July 23 and 24, 2025, adopted the following:
1. City Council approve in-year budget adjustments to the 2024-2033 Approved Capital Budget and Plan as detailed in Appendix 4 to the report (July 2, 2025) from the Chief Financial Officer and Treasurer.
Background Information (Committee)
https://www.toronto.ca/legdocs/mmis/2025/ex/bgrd/backgroundfile-257072.pdf
Appendix 1 - Capital Variance Summary for the Twelve Months Ended December 31, 2024
https://www.toronto.ca/legdocs/mmis/2025/ex/bgrd/backgroundfile-257073.pdf
Appendix 2a - Capital Projects Fully Closed for Year 2024
https://www.toronto.ca/legdocs/mmis/2025/ex/bgrd/backgroundfile-257074.pdf
Appendix 2b - Capital Projects Partial Closed for Year 2024
https://www.toronto.ca/legdocs/mmis/2025/ex/bgrd/backgroundfile-257075.pdf
Appendix 3 - Major Capital Projects
https://www.toronto.ca/legdocs/mmis/2025/ex/bgrd/backgroundfile-257076.pdf
Appendix 4 - In-Year Adjustments for the Twelve months Ended December 31, 2024
https://www.toronto.ca/legdocs/mmis/2025/ex/bgrd/backgroundfile-257077.pdf
Appendix 5 - Capital Variance Dashboard by Program and Agency
https://www.toronto.ca/legdocs/mmis/2025/ex/bgrd/backgroundfile-257078.pdf
EX25.7 - Capital Variance Report for the Twelve Months Ended December 31, 2024
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
Committee Recommendations
The Executive Committee recommends that:
1. City Council approve in-year budget adjustments to the 2024-2033 Approved Capital Budget and Plan as detailed in Appendix 4 to the report (July 2, 2025) from the Chief Financial Officer and Treasurer.
Origin
Summary
The purpose of this report is to provide City Council with the City of Toronto’s capital spending for the twelve-month period ended December 31, 2024. Furthermore, this report seeks Council's approval for in-year budget adjustments to the 2024 Approved Capital Budget and Plan to align with the year-end funding requirements.
As illustrated in Table 1 below, the City's 2024 capital expenditure was $4.740 billion or 73.8 percent of the 2024 Approved Capital Budget of $6.422 billion for the period ended December 31, 2024.
- Tax Supported City Programs and Agencies reported capital expenditures of $3.653 billion representing 73.4 percent of their collective 2024 Approved Capital Budget of $4.976 billion.
- Rate Supported City Programs reported capital expenditures of $1.086 billion, representing 75.1 percent of their collective 2024 Approved Capital Budget of $1.446 billion.
Table 1: Capital Variance Summary
|
Table 1 |
|||
|
Corporate Capital Variance Summary |
|||
|
for the Period Ended December 31, 2024 |
|||
|
|
2024 Approved Budget* |
2024 YE Actual |
|
|
|
$M |
$M |
% |
|
City Operations |
3,313.9 |
2,107.6 |
63.6% |
|
Agencies |
1,661.9 |
1,545.6 |
93.0% |
|
Tax Supported: |
4,975.8 |
3,653.3 |
73.4% |
|
Rate Supported: |
1,445.8 |
1,086.3 |
75.1% |
|
TOTAL |
6,421.6 |
4,739.6 |
73.8% |
|
*Note: Includes carry forward funding |
|||
In 2024, the City’s actual capital delivery continued its upward trend, building from the progress made in 2023. The capital spending totaled $4.740 billion, with a spending rate of 73.8 percent, reflect an improvement over 2023, when capital expenditures were $4.219 billion with a spending rate of 71.4 percent. The spending rate is defined as the actual capital expenditures as a percentage of the full year budget including in-year budget adjustments and carry forward funding from prior years' unspent budget.
The improved spending rate is largely attributable to the City’s sustained focus on prioritizing capital delivery, supported by strengthened budget planning process. This approach has enabled City Programs and Agencies to accelerate project timelines and enhance overall execution The achievements were made possible by the coordinated efforts of City Council, Divisions, and Agencies.
Background Information
https://www.toronto.ca/legdocs/mmis/2025/ex/bgrd/backgroundfile-257072.pdf
Appendix 1 - Capital Variance Summary for the Twelve Months Ended December 31, 2024
https://www.toronto.ca/legdocs/mmis/2025/ex/bgrd/backgroundfile-257073.pdf
Appendix 2a - Capital Projects Fully Closed for Year 2024
https://www.toronto.ca/legdocs/mmis/2025/ex/bgrd/backgroundfile-257074.pdf
Appendix 2b - Capital Projects Partial Closed for Year 2024
https://www.toronto.ca/legdocs/mmis/2025/ex/bgrd/backgroundfile-257075.pdf
Appendix 3 - Major Capital Projects
https://www.toronto.ca/legdocs/mmis/2025/ex/bgrd/backgroundfile-257076.pdf
Appendix 4 - In-Year Adjustments for the Twelve months Ended December 31, 2024
https://www.toronto.ca/legdocs/mmis/2025/ex/bgrd/backgroundfile-257077.pdf
Appendix 5 - Capital Variance Dashboard by Program and Agency
https://www.toronto.ca/legdocs/mmis/2025/ex/bgrd/backgroundfile-257078.pdf