Item - 2025.BA151.13
Tracking Status
- This item was considered by Bid Award Panel on September 25, 2025 and was adopted without amendment.
BA151.13 - Award of Doc5276373158 to Alliance Verdi Civil Inc. for Culvert Rehabilitation Within Scarborough for Engineering and Construction Services
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- 20 - Scarborough Southwest, 21 - Scarborough Centre
Panel Decision
The Bid Award Panel adopted the following:
1. Bid Award Panel grant authority to award the contract in accordance with the Contract Details set out in the report (September 18, 2025) from the Chief Procurement Officer:
Solicitation Number:
Request for Tender Doc5276373158, Contract 25ECS-BE-07PM
Description:
Culvert Rehabilitation of St. Clair Avenue over Massey Creek (ID88), Brimely Road over West Highland Creek (ID385), and Penworth Road over Massey Creek (ID919)
Recommended Supplier:
Alliance Verdi Civil Inc.
Contract Award Value:
$ 4,053,788 net of all applicable taxes and charges
$ 4,580,780 including HST and all applicable charges
$ 4,125,134 net of HST recoveries
Contract is expected to start on date of award and end on December 31, 2028.
Origin
Summary
Solicitation Issued: August 5, 2025 Solicitation Closed: August 29, 2025
Number of Addenda Issued: Five (5)
Number of Bids: Five (5)
Table 2: Summary of Bids Received including bid price
|
Supplier Name |
Bid Price (excluding H.S.T.) |
|
Alliance Verdi Civil Inc. |
$3,378,156.40* |
|
Belor Construction Ltd. |
$3,383,362.80 |
|
2220742 Ontario Ltd. o/a Bronte Construction |
$4,220,853.23 |
|
Graham Bros. Construction Limited |
$4,281,640.80 |
|
Clearwater Structures Inc. |
$4,678,999.66 |
* Pursuant to the Request for Tender document, the contract award value includes contingency.
Background Information
https://www.toronto.ca/legdocs/mmis/2025/ba/bgrd/backgroundfile-258646.pdf
Motions
Moved by Lena Dianda.
Vote (Adopt Item)
|
Result: |
Majority Required |
|
Yes: |
Leah Ross (Chair), Lena Dianda, Diana Santucci |
|
No: |
|
|
Absent: |
David McLeod |