Item - 2025.BA148.9
Tracking Status
- This item was considered by Bid Award Panel on September 3, 2025 and was adopted without amendment.
BA148.9 - Award of Doc5257015875 to D. Crupi & Sons Limited for Major Road Resurfacing and Bikeway Construction for Engineering and Construction Services
- Decision Type:
- ACTION
- Status:
- Adopted
- Ward:
- 7 - Humber River - Black Creek
Panel Decision
The Bid Award Panel adopted the following:
1. Bid Award Panel grant authority to award the contract in accordance with the Contract Details set out in the report (August 28, 2025) from the Chief Procurement Officer:
Solicitation Number:
Request for Tender Doc5257015875, Contract Number 25ECS-RD-03MR
Description:
Major Road Resurfacing and Bikeway Construction on York Gate Boulevard from Jane Street to Finch Avenue West
Recommended Supplier:
D. Crupi & Sons Limited
Contract Award Value:
$1,257,177 net of all applicable taxes and charges
$1,420,610 including HST and all applicable charges
$1,279,303 net of HST recoveries
Contract is expected to start on date of award and end on December 31, 2025.
Origin
Summary
Solicitation Issued: July 16, 2025 Solicitation Closed: August 6, 2025
Number of Addenda Issued: One (1)
Number of Bids: Six (6)
Table 2: Summary of Bids Received including bid price
Supplier Name |
Bid Price (excluding H.S.T.) |
D. Crupi & Sons Limited |
$1,142,888.00* |
D. Martino Construction Limited |
$1,250,000.00 |
Sanscon Construction Ltd. |
$1,276,435.00 |
Four Seasons Site Development Ltd. |
$1,490,633.00 |
CRCE Construction Ltd. |
$1,509,260.00 |
Pave-Al Limited |
$1,538,176.00 |
* Pursuant to the Request for Tender document, the contract award value includes contingency
Background Information
https://www.toronto.ca/legdocs/mmis/2025/ba/bgrd/backgroundfile-258045.pdf
Motions
Moved by Lena Dianda.
Vote (Adopt Item)
Result: |
Majority Required |
Yes: |
Leah Ross (Chair), David McLeod, Lena Dianda, Diana Santucci |
No: |
|
Absent: |