Item - 2024.ZB10.6
Tracking Status
- This item was considered by Toronto Zoo on May 31, 2024 and was adopted without amendment.
ZB10.6 - Rouge Valley Erosion Control - Buried Utilities Relocation Project
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
Board Decision
The Board of Management of the Toronto Zoo :
1. Approved an increase in the commitment to Clearway Utilities by $192,521.49 from $1,046,005.00 to $1,238,526.49.
Origin
(May 17, 2024) Report from the Director, Facilities and Infrastructure
Summary
This report seeks approval to increase the budget to complete the Buried Utilities Relocation Project.
Background Information
(May 17, 2024)
Report from the Director, Facilities and Infrastructure on Rouge Valley Erosion Control - Buried Utilities Relocation Project
https://www.toronto.ca/legdocs/mmis/2024/zb/bgrd/backgroundfile-246019.pdf
https://www.toronto.ca/legdocs/mmis/2024/zb/bgrd/backgroundfile-246019.pdf
Motions
Motion
to Adopt Item
moved by
Ivan Hon
(Carried)