Item - 2024.TE14.29

Tracking Status

  • This item was considered by Toronto and East York Community Council on June 11, 2024 and was adopted without amendment. City Council has delegated authority for this matter to the Toronto and East York Community Council and therefore, the decision is final.

TE14.29 - 292-298 Dundas Street West - Construction Staging Area Time Extension

Decision Type:
ACTION
Status:
Adopted
Schedule Type:
Delegated
Ward:
11 - University - Rosedale

Community Council Decision

The Toronto and East York Community Council:

 

1. Authorized the continuation of the closure of the west sidewalk on St. Patrick Street from Dundas Street West to a point 53 metres north and a 2.3 metre section of the southbound curb lane on St. Patrick Street between Dundas Street West and a point 27 metres north, from July 2, 2024 to September 1, 2025 inclusive.

 

2. Directed the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

3. Directed the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.

 

4. Directed that Dundas Street West be returned to its pre-construction traffic regulations when the project is completed.

Origin

(May 2, 2024) Report from the Director, Traffic Management, Transportation Services

Summary

This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision.

 

Tribute (Mc-Caul Street) Limited, is constructing a 32-storey residential condominium building at 292-298 Dundas Street West. The west sidewalk and a 2.3 metre wide portion of the southbound curb lane on St. Patrick Street abutting the site is currently closed for construction staging operations.

 

Toronto and East York Community Council, at its meeting on May 26, 2022, approved the subject construction staging area on St. Patrick Street from September 1, 2022 to July 1, 2024. The developer has requested a time extension on St. Patrick Street, due to a variety of construction delays and a recently approved minor variance decision permitting the addition of three-storeys.

 

Transportation Services is requesting authorization to extend the duration of the construction staging area on St. Patrick Street for an additional 14 months, from July 2, 2024 to September 1, 2025 to allow for the construction of the development to be completed.

Background Information

(May 2, 2024) Report and Attachment 1 from the Director, Traffic Management, Transportation Services on 292-298 Dundas Street West - Construction Staging Area Time Extension
https://www.toronto.ca/legdocs/mmis/2024/te/bgrd/backgroundfile-245402.pdf

Motions

Motion to Adopt Item moved by Councillor Dianne Saxe (Carried)
Source: Toronto City Clerk at www.toronto.ca/council