Item - 2024.TE12.38

Tracking Status

  • City Council adopted this item on April 17 and 18, 2024 without amendments and without debate.
  • This item was considered by the Toronto and East York Community Council on April 3, 2024 and adopted without amendment. It will be considered by City Council on April 17 and 18, 2024.

TE12.38 - 400-420 King Street West - Construction Staging Area Time Extension

Decision Type:
ACTION
Status:
Adopted on Consent
Ward:
10 - Spadina - Fort York

City Council Decision

City Council on April 17 and 18, 2024, adopted the following:

 

1. City Council authorize the continuation of the closure of the north sidewalk and westbound curb lane on King Street West, between Charlotte Street and a point 66 metres east and provision of a temporary pedestrian walkway within the closed portion of the westbound curb lane from September 1, 2024 to December 31, 2026.

 

2. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

3. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor

 

4. City Council direct that King Street West be returned to its pre-construction traffic regulations when the project is completed.

Background Information (Community Council)

(February 16, 2024) Report and Attachment 1 from the Director, Traffic Management, Transportation Services on 400-420 King Street West - Construction Staging Area Time Extension
https://www.toronto.ca/legdocs/mmis/2024/te/bgrd/backgroundfile-243725.pdf

TE12.38 - 400-420 King Street West - Construction Staging Area Time Extension

Decision Type:
ACTION
Status:
Adopted
Ward:
10 - Spadina - Fort York

Community Council Recommendations

The Toronto and East York Community Council recommends that:  

 

1. City Council authorize the continuation of the closure of the north sidewalk and westbound curb lane on King Street West, between Charlotte Street and a point 66 metres east and provision of a temporary pedestrian walkway within the closed portion of the westbound curb lane, from September 1, 2024 to December 31, 2026.

 

2. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

3. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor

 

4. City Council direct that King Street West be returned to its pre-construction traffic regulations when the project is completed.

Origin

(February 16, 2024) Report from the Director, Traffic Management, Transportation Services

Summary

As the Toronto Transit Commission (TTC) operates a transit service on King Street West City Council approval of this report is required.

 

TMG Builders is constructing a 49-storey mixed use residential condominium development at 400-420 King Street West. The north sidewalk on King Street West and the east sidewalk on Charlotte Street is currently closed for construction staging operations. City Council, at its meeting on December 15, 2021, approved the closure of the east sidewalk on Charlotte Street until December 31, 2026 and the north sidewalk and a 2.6 metre-wide portion of the westbound curb lane on King Street West, between Charlotte Street and a point 66 metres east, from July 1, 2022 to August 31, 2024.

 

Transportation Services is requesting authorization to extend the duration of the construction staging area on King Street West for an additional 28 months, from September 1, 2024 to December 31, 2026 to allow for the construction of the development to be completed.

Background Information

(February 16, 2024) Report and Attachment 1 from the Director, Traffic Management, Transportation Services on 400-420 King Street West - Construction Staging Area Time Extension
https://www.toronto.ca/legdocs/mmis/2024/te/bgrd/backgroundfile-243725.pdf

Motions

Motion to Adopt Item moved by Deputy Mayor Ausma Malik (Carried)
Source: Toronto City Clerk at www.toronto.ca/council