Item - 2024.SC11.15

Tracking Status

  • City Council adopted this item on March 20 and 21, 2024 without amendments and without debate.
  • This item was considered by the Scarborough Community Council on February 16, 2024 and adopted without amendment. It will be considered by City Council on March 20 and 21, 2024.
  • See also By-law 812-2024

SC11.15 - Assumption of Services, Registered Plan 66M-2461, Portia Street Subdivision, Scarborough (90 Morningside Avenue)

Decision Type:
ACTION
Status:
Adopted on Consent
Ward:
24 - Scarborough - Guildwood

City Council Decision

City Council on March 20 and 21, 2024, adopted the following:

 

1. City Council assume the services installed within Portia Street and that the City formally assume the road within the Registered Plan of Subdivision 66M-2461.

 

2. City Council authorize the Acting Director, Engineering Review to release the performance guarantee held with respect to the municipal services in accordance with the Subdivision Agreement.

 

3. City Council direct that an assumption By-law be prepared to assume the public highway and municipal services within the Registered Subdivision 66M-2461.

 

4. City Council authorize and direct the City Solicitor to register the assumption By-law in the Land Registry Office at the expense of the Owner.

 

5. City Council authorize the appropriate City Officials to take the necessary action to give effect to City Council's decision.

 

6. City Council authorize the appropriate City Officials to transfer ownership of the street lighting system constructed with Registered Plan of Subdivision 66M-2461 to Toronto Hydro Corporation.

Background Information (Community Council)

(January 9, 2024) Report and Attachment 1 from the Acting Director, Engineering Review, Engineering and Construction Services on Assumption of Services, Registered Plan 66M-2461, Portia Street Subdivision, Scarborough (90 Morningside Avenue)
https://www.toronto.ca/legdocs/mmis/2024/sc/bgrd/backgroundfile-242758.pdf

SC11.15 - Assumption of Services, Registered Plan 66M-2461, Portia Street Subdivision, Scarborough (90 Morningside Avenue)

Decision Type:
ACTION
Status:
Adopted
Ward:
24 - Scarborough - Guildwood

Community Council Recommendations

The Scarborough Community Council recommends that:  

 

1. City Council assume the services installed within Portia Street and that the City formally assume the road within the Registered Plan of Subdivision 66M-2461.

 

2.  City Council authorize the Acting Director, Engineering Review to release the performance guarantee held with respect to the municipal services in accordance with the Subdivision Agreement.

 

3. City Council direct that an assumption By-law be prepared to assume the public highway and municipal services within the Registered Subdivision 66M-2461.

 

4. City Council authorize and direct the City Solicitor to register the assumption By-law in the Land Registry Office at the expense of the Owner.

 

5. City Council authorize the appropriate City Officials to take the necessary action to give effect thereto.

 

6. City Council authorize the appropriate City Officials to transfer ownership of the street lighting system constructed with Registered Plan of Subdivision 66M-2461to Toronto Hydro.

Origin

(January 9, 2024) Report from the Acting Director, Engineering Review, Engineering and Construction Services

Summary

This report recommends that the municipal services under the terms of the Subdivision Agreement for Plan 66M-2461, dated December 19, 2008 between Sentex Properties Ltd. and the City of Toronto be assumed by the City.

Background Information

(January 9, 2024) Report and Attachment 1 from the Acting Director, Engineering Review, Engineering and Construction Services on Assumption of Services, Registered Plan 66M-2461, Portia Street Subdivision, Scarborough (90 Morningside Avenue)
https://www.toronto.ca/legdocs/mmis/2024/sc/bgrd/backgroundfile-242758.pdf

Motions

Motion to Adopt Item moved by Councillor Paul Ainslie (Carried)
Source: Toronto City Clerk at www.toronto.ca/council