Item - 2024.SC11.10
Tracking Status
- City Council adopted this item on March 20, 2024 without amendments and without debate.
- This item was considered by Scarborough Community Council on February 16, 2024 and was adopted with amendments. It will be considered by City Council on March 20, 2024.
SC11.10 - Metrolinx Scarborough Subway Extension - Time Extension of Temporary Sidewalk Closure on McCowan Road
- Decision Type:
- ACTION
- Status:
- Adopted on Consent
- Ward:
- 23 - Scarborough North
City Council Decision
City Council on March 20 and 21, 2024, adopted the following:
1. City Council authorize the continuation of the temporary closure of the east sidewalk on McCowan Road, between Sheppard Avenue East and Nugget Avenue, from April 1, 2024, to December 31, 2024, inclusive, to facilitate the Scarborough Subway Extension tunnel construction work.
2. City Council direct that the east sidewalk and boulevard space on McCowan Road, between Sheppard Avenue East and Nugget Avenue, be returned to its pre-construction or better condition when the project is completed.
3. City Council request the General Manager, Transportation Services to request Metrolinx to provide an update on the construction timelines of the Scarborough Subway Extension project, including the tunnel boring operations prior to requesting any time extension for the temporary closure of the east sidewalk on McCowan Road, between Sheppard Avenue East and Nugget Avenue beyond December 31, 2024.
Background Information (Community Council)
https://www.toronto.ca/legdocs/mmis/2024/sc/bgrd/backgroundfile-242744.pdf
SC11.10 - Metrolinx Scarborough Subway Extension - Time Extension of Temporary Sidewalk Closure on McCowan Road
- Decision Type:
- ACTION
- Status:
- Amended
- Ward:
- 23 - Scarborough North
Community Council Recommendations
The Scarborough Community Council recommends that:
1. City Council authorize the continuation of the temporary closure of the east sidewalk
on McCowan Road, between Sheppard Avenue East and Nugget Avenue, from April 1, 2024, to December 31, 2024, inclusive, to facilitate the Scarborough Subway Extension tunnel construction work.
2. City Council direct that the east sidewalk and boulevard space on McCowan Road, between Sheppard Avenue East and Nugget Avenue, be returned to its pre-construction or better condition when the project is completed.
3. City Council request the General Manager, Transportation Services to request Metrolinx to provide an update on the construction timelines of the Scarborough Subway Extension project, including the tunnel boring operations prior to requesting any time extension for the temporary closure of the east sidewalk on McCowan Road, between Sheppard Avenue East and Nugget Avenue beyond December 31, 2024.
Origin
Summary
As the Toronto Transit Commission (TTC) operates a transit service on McCowan Road, City Council approval of this report is required.
Currently, Metrolinx's contractor, Strabag ("the Project Co.") is actively engaged in tunnel boring operations at the designated site in the north-east quadrant of Sheppard Avenue East and McCowan Road. The City Council-approved temporary closure of the east sidewalk on McCowan Road, between Sheppard Avenue East and Nugget Avenue, has been implemented to mitigate potential conflicts between pedestrians and significant flow of inbound and outbound construction vehicles. The approved sidewalk closure is set to expire on March 31, 2024.
Metrolinx has submitted a request for an extension of the temporary sidewalk closure until December 31, 2025. This extension is sought to accommodate the ongoing tunnel boring operations, which have experienced schedule adjustments due to challenges associated with the tunnel boring machine operation and maintenance. Subject to City Council approval of the requested time extension, with the east sidewalk closure in place, pedestrians will continue to utilize the west sidewalk on McCowan Road by safely crossing at the signalized intersections of McCowan Road and Sheppard Avenue East and McCowan Road and Nugget Avenue. Finally, the Project Co. will continue to monitor pedestrian safety along the north sidewalk on Sheppard Avenue East abutting the site by deploying traffic control persons at the site accesses.
Background Information
https://www.toronto.ca/legdocs/mmis/2024/sc/bgrd/backgroundfile-242744.pdf
Motions
That the Scarborough Community Council:
1. Amend Recommendation 1 by deleting "December 31, 2025" and replacing it with "December 31, 2024" so that it now reads:
1. City Council authorize the continuation of the temporary closure of the east sidewalk on McCowan Road, between Sheppard Avenue East and Nugget Avenue, from April 1, 2024, to December 31, 2024, inclusive, to facilitate the Scarborough Subway Extension tunnel construction work.
2. Add the following new Recommendation:
"City Council request the General Manager, Transportation Services to request Metrolinx to provide an update on the construction timelines of the Scarborough Subway Extension project, including the tunnel boring operations prior to requesting any time extension for the temporary closure of the east sidewalk on McCowan Road, between Sheppard Avenue East and Nugget Avenue beyond December 31, 2024."
Vote (Amend Item (Additional)) Feb-16-2024
Result: Carried | Majority Required |
---|---|
Total members that voted Yes: 3 | Members that voted Yes are Paul Ainslie (Chair), Parthi Kandavel, Jamaal Myers |
Total members that voted No: 1 | Members that voted No are Michael Thompson |
Total members that were Absent: 2 | Members that were absent are Nick Mantas, Jennifer McKelvie |