Item - 2024.PB23.4

Tracking Status

  • This item was considered by the Toronto Preservation Board on October 17, 2024. The Committee received the item for information only. No further action will be taken on this item.

PB23.4 - Update on Phase 2 Implementation of Bill 23

Decision Type:
Presentation
Status:
Received
Wards:
All

Board Decision

The Toronto Preservation Board received this item for information.

Decision Advice and Other Information

Paul Maka, Project Manager, Heritage Planning, Urban Design, City Planning and Adrian Gamble, Planner, Urban Design, Heritage Planning, City Planning gave a presentation on Update on Phase 2 Implementation of Bill 23.

Origin

(October 17, 2024) Presentation from the Senior Manager, Heritage Planning, Urban Design, City Planning and the Project Manager, Heritage Registrar, Urban Design, City Planning

Summary

Mary MacDonald, Senior Manager, Heritage Planning and Paul Maka, Project Manager, Heritage Registrar will provide an update on Phase 2 implementation of Bill 23.

Background Information

Staff Presentation on Update on Phase 2 Implementation of Bill 23
https://www.toronto.ca/legdocs/mmis/2024/pb/bgrd/backgroundfile-249589.pdf

Motions

Motion to Receive Item moved by Geoff Kettel (Carried)

That the item be received for information.