Item - 2024.GG16.7

Tracking Status

GG16.7 - Award of 2 Contracts of Tender Doc4377242742 to Drainstar Contracting Ltd. and GIP Paving Inc. for Construction Services and Amendment of Professional Services During Construction Purchase Order No. 6052519 with CH2M Hill Canada Ltd. for the Fairbank Silverthorn Basement Flooding Protection Project

Decision Type:
ACTION
Status:
Adopted
Wards:
5 - York South - Weston, 8 - Eglinton - Lawrence, 9 - Davenport, 12 - Toronto - St. Paul's

Committee Decision

The General Government Committee:

 

1. In accordance with Section 195-8.4 of Toronto Municipal Code Chapter 195 (Purchasing By-Law), authorized the Chief Engineer and Executive Director to award Request for Tender Doc4377242742, Contract Number 23ECS-MI-02FS, for the construction of Local Storm Collectors West and other improvements of the Fairbank Silverthorn Basement Flooding Protection Program project, in the amount of $65,939,065 net of all applicable taxes and charges ($67,099,593 net of Harmonized Sales Tax recoveries) to Drainstar Contracting Ltd., having submitted the lowest complaint bid and meeting the specifications in conformance with the Tender requirements.

 

2. In accordance with Section 195-8.4 of Toronto Municipal Code Chapter 195 (Purchasing By-Law), authorized the Chief Engineer and Executive Director to award Request for Tender Doc4377242742, Contract Number 23ECS-MI-03FS, for the construction of Local Storm Collectors East and other improvements of the Fairbank Silverthorn Basement Flooding Protection Program project, in the amount of $89,101,279 net of all applicable taxes and charges ($90,669,462 net of Harmonized Sales Tax recoveries) to GIP Paving Inc., having submitted the lowest complaint bid and meeting the specifications in conformance with the Tender requirements.

 

3. In accordance with Section 71-11.1.C of Toronto Municipal Code Chapter 71 (Financial Control By-Law), authorized the amendment to Purchase Order Number 6052519 with CH2M Hill Canada Ltd., for providing Professional Engineering Services during Construction for three construction contracts of the Fairbank Silverthorn Basement Flooding Protection Program Project in the amount of $10,500,000 net of all applicable taxes and charges ($10,684,800 net of Harmonized Sales Tax recoveries), revising the current Purchase Order value from $14,971,781 net of all applicable taxes and charges ($15,235,285 net of Harmonized Sales Tax recoveries) to $25,471,781 net of all applicable taxes and charges ($25,920,085 net of Harmonized Sales Tax recoveries).

Origin

(August 30, 2024) Report from the Chief Engineer and Executive Director, Engineering and Construction Services, and the Chief Procurement Officer, Purchasing and Materials Management

Summary

The purpose of this report is to advise of the results of the Request for Tender Doc4377242742 which includes two construction contracts, Contract Number 23ECS-MI-02FS and Contract Number 23ECS-MI-03FS, for the construction of new storm collectors and other improvements in the Basement Flooding Protection Program Study Area 3, also referred to as the Fairbank Silverthorn Project. The report recommends entering into agreements with (1) Drainstar Contracting Ltd., in the amount of $65,939,065 net of all applicable taxes and charges ($67,099,593 net of Harmonized Sales Tax recoveries), for the construction of Contract Number 23ECS-MI-02FS - Local Storm Collectors West, and (2) GIP Paving Inc., in the amount of $89,101,279 net of all applicable taxes and charges ($90,669,462 net of Harmonized Sales Tax recoveries), for the construction of Contract Number 23ECS-MI03FS - Local Storm Collectors East. Pursuant to the Request for Tender document the contract award value includes contingency.  

 

This report also requests authority to amend Purchase Order Number 6052519 issued to CH2M Hill Canada Ltd., referred to as CH2M Hill, under Request for Proposal number 9117-18-7185 to provide Engineering Services during Construction for the Fairbank Silverthorn Project in the amount of $10,500,000 net of all applicable taxes and charges ($10,684,800 net of Harmonized Sales Tax recoveries). This amendment will increase the current purchase order value from $14,971,781 net of all applicable taxes and charges ($15,235,285 net of Harmonized Sales Tax recoveries) to $25,471,781 net of all applicable taxes and charges ($25,920,085 net of Harmonized Sales Tax recoveries). This purchase order amendment is necessary for additional project management, contract administration, site inspection and engineering services during the construction of three major contracts for the Fairbank Silverthorn Project.

Background Information

(September 16, 2024) Revised Report from the Chief Engineer and Executive Director, Engineering and Construction Services and the Chief Procurement Officer, Purchasing and Materials Management on Award of 2 Contracts of Tender Doc4377242742 to Drainstar Contracting Ltd. and GIP Paving Inc. for Construction Services and Amendment of Professional Services During Construction Purchase Order No. 6052519 with CH2M Hill Canada Ltd. for the Fairbank Silverthorn Basement Flooding Protection Project
https://www.toronto.ca/legdocs/mmis/2024/gg/bgrd/backgroundfile-248701.pdf
(August 30, 2024) Report from the Chief Engineer and Executive Director, Engineering and Construction Services and the Chief Procurement Officer, Purchasing and Materials Management on Award of 2 Contracts of Tender Doc4377242742 to Drainstar Contracting Ltd. and GIP Paving Inc. for Construction Services and Amendment of Professional Services During Construction Purchase Order No. 6052519 with CH2M Hill Canada Ltd. for the Fairbank Silverthorn Basement Flooding Protection Project
https://www.toronto.ca/legdocs/mmis/2024/gg/bgrd/backgroundfile-248342.pdf
Attachment 1 - Class EA Solution
https://www.toronto.ca/legdocs/mmis/2024/gg/bgrd/backgroundfile-248343.pdf
Attachment 2 - Current Project Scope (Includes all three Construction Contracts)
https://www.toronto.ca/legdocs/mmis/2024/gg/bgrd/backgroundfile-248344.pdf
Attachment 3 - Fairness Monitor Report
https://www.toronto.ca/legdocs/mmis/2024/gg/bgrd/backgroundfile-248345.pdf

Motions

Motion to Adopt Item moved by Councillor Stephen Holyday (Carried)
Source: Toronto City Clerk at www.toronto.ca/council