Item - 2024.EX16.18
Tracking Status
- City Council adopted this item on July 24 and 25, 2024 without amendments and without debate.
- This item was considered by the Executive Committee on July 16, 2024 and adopted without amendment. It will be considered by City Council on July 24 and 25, 2024.
- See also 2024.EX17.16
EX16.18 - Toronto Water 2024 Capital Budget and 2025-2033 Capital Plan Adjustments
- Decision Type:
- ACTION
- Status:
- Adopted on Consent
- Wards:
- All
City Council Decision
City Council on July 24 and 25, 2024, adopted the following:
1. City Council authorize the reallocation of cashflows and corresponding funding within Toronto Water’s 2024 Capital Budget and 2025-2033 Capital Plan in the amount of $29.405 million, for acceleration and deferral of projects, as presented in Schedule A (Parts A and B) to the report (June 21, 2024) from the General Manager, Toronto Water, with a zero Budget impact.
2. City Council authorize the reallocation of project costs, cashflows and corresponding funding in Toronto Water's 2024 Capital Budget and 2025-2033 Capital Plan in the amount of $15.983 million from projects that have been awarded under budget or completed to those requiring additional funding in the same amount as presented in Schedule A (Part C) to the report (June 21, 2024) from the General Manager, Toronto Water, with a zero Budget impact.
Background Information (Committee)
https://www.toronto.ca/legdocs/mmis/2024/ex/bgrd/backgroundfile-247112.pdf
Communications (City Council)
EX16.18 - Toronto Water 2024 Capital Budget and 2025-2033 Capital Plan Adjustments
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
Committee Recommendations
The Executive Committee recommends that:
1. City Council authorize the reallocation of cashflows and corresponding funding within Toronto Water’s 2024 Capital Budget and 2025-2033 Capital Plan in the amount of $29.405 million, for acceleration and deferral of projects, as presented in Schedule A (Parts A and B) to the report (June 21, 2024) from the General Manager, Toronto Water, with a zero Budget impact.
2. City Council authorize the reallocation of project costs, cashflows and corresponding funding in Toronto Water's 2024 Capital Budget and 2025-2033 Capital Plan in the amount of $15.983 million from projects that have been awarded under budget or completed to those requiring additional funding in the same amount as presented in Schedule A (Part C) to the report (June 21, 2024) from the General Manager, Toronto Water, with a zero Budget impact.
Origin
Summary
This report requests City Council's authority to amend Toronto Water's 2024 Capital Budget and 2025-2033 Capital Plan by adjusting project cash flows contained within the Budget and Plan, respectively, to align forecasted project accelerations and deferrals. Additional reallocations to project cashflows and project costs are requested where project expenditures exceed the current approved cashflows and project costs. These reallocations will allow Toronto Water to continue to deliver projects within its capital plan. The adjustments will have a zero dollar impact on the 2024 Capital Budget and 2025-2033 Capital Plan and will align the budget and plan with Toronto Water's capital project delivery schedule and program requirements.
Background Information
https://www.toronto.ca/legdocs/mmis/2024/ex/bgrd/backgroundfile-247112.pdf