Item - 2024.BA112.2

Tracking Status

  • This item was withdrawn from the agenda of the Bid Award Panel meeting on December 23, 2024. No further action will be taken on this item.

BA112.2 - Award of Doc4527040342 to Midome Construction Services Ltd. for Watermain Replacement, Sewer Replacement, Laneway Reconstruction and Neighbourhood Improvements on Various Roads for Engineering and Construction Services

Decision Type:
ACTION
Status:
Withdrawn
Wards:
5 - York South - Weston, 9 - Davenport, 11 - University - Rosedale

Panel Decision

Item BA112.2 was withdrawn from the agenda.

Origin

(December 18, 2024) Report from the Chief Procurement Officer

Summary

Solicitation Issued: April 19, 2024         Solicitation Closed: May 16, 2024

Number of Addenda Issued: Two (2)

Number of Bids: Five (5)

 

Table 2: Summary of Bids Received including bid price

Supplier Name

Bid Price (excluding Harmonized Sales Tax)

Midome Construction Services Ltd.

$16,444,000.00 *

Gio Crete Construction Ltd.

$16,490,860.00

2489960 Ontario Inc. o/a Kore Infrastructure

Group**

$16,660,000.00

Four Seasons Site Development Ltd.

$16,865,100.00

CRCE Construction Ltd.

$20,382,130.00

 

* Pursuant to the Request for Tender document, the contract award price includes contingency.

** The bid was submitted as a joint venture.

Background Information

(December 18, 2024) Report from the Chief Procurement Officer on Award of Doc4527040342 to Midome Construction Services Ltd. for Watermain Replacement, Sewer Replacement, Laneway Reconstruction and Neighbourhood Improvements on Various Roads for Engineering and Construction Services
https://www.toronto.ca/legdocs/mmis/2024/ba/bgrd/backgroundfile-251728.pdf

Motions

Motion to Withdraw an Item (Carried)

Moved by Lena Dianda.

 

Vote (Withdraw Item)

 

Result:

Majority Required

Yes:

David McLeod (Vice Chair), Diana Santucci, Lena Dianda

No:

 

Absent:

Leah Ross (Chair)

Source: Toronto City Clerk at www.toronto.ca/council