ZB6.6 - Community Conservation Centre Phasing and Budget Increase

Decision Type:
ACTION
Status:
Adopted
Wards:
All

Board Decision

The Board of Management of the Toronto Zoo: :  

 

1. Approved an increase in the project budget for the Community Conservation Centre (TZC3) from $41.3 million to $64.0 million inclusive of soft costs, with the additional costs being supported through a reallocation of funds within the 10-year capital plan, the Toronto Zoo Wildlife Conservancy and external funding partners; the reallocation of funds in the 10-year capital plan is yet to be approved by the City.

 

2. Approved proceeding with phase one of the approved project (the community use and classroom facilities) within the previously approved budget, with Phase two to commence pending approval of the 2024-2033 capital budget by Toronto City Council in February, 2024.

Origin

(October 6, 2023) Report from the Chief Executive Officer, Toronto Zoo

Summary

This report recommends an increase to the project budget for the Community Conservation Centre (Front Entrance and Welcome Area) and adjusts the scope to advance the project in a phased manner.

Background Information

(October 6, 2023) Report from the Chief Executive Officer, Toronto Zoo on Community Conservation Centre Phasing and Budget Increase
https://www.toronto.ca/legdocs/mmis/2023/zb/bgrd/backgroundfile-239848.pdf

Motions

Motion to Adopt Item moved by Ms. Cynthia Holmes (Carried)