TE7.40 - 25 Ontario Street - Construction Staging Area Time Extension

Decision Type:
ACTION
Status:
Amended
Schedule Type:
Delegated
Ward:
13 - Toronto Centre

Community Council Decision

The Toronto and East York Community Council:

 

1.  Authorized the continuation of closure of the east sidewalk and a 3.3 metre wide portion of the southbound curb lane on Ontario Street, between Adelaide Street East and a point 47 metres south of Adelaide Street East, to April 30, 2024.

 

2. Directed the applicant to continue to sweep and pressure wash the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe.

 

3. Directed the applicant to continue to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night.

 

4. Directed the applicant to continue to clearly consult and communicate all construction, parking and road occupancy impacts with local Business Improvement Areas, resident associations and George Brown College administration, in advance of any physical road modifications.

 

5. Directed the applicant, in consultation with Transportation Services, to continue to maintain any bike lanes, and install appropriate signage to inform drivers and cyclists of any changes to the cycling lanes and to ensure that pedestrians, cyclists and motorists safety are considered at all times.

 

6. Directed the applicant to continue to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and the Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public.

 

7. Directed the applicant to continue to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and the Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public.

 

8. Directed the applicant to continue to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired.

 

9. Directed the applicant to continue to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

10. Directed the applicant to continue to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.

 

11. Directed the applicant to continue a Construction Management Working Group that meets monthly and invite local stakeholders including Transportation Services, Municipal Licensing and Standards, Toronto Buildings, adjacent neighbours, local resident groups and local Business Improvement Areas.

 

12. Directed that Ontario Street be returned to its pre-construction traffic and parking regulations when the project is complete.

Origin

(August 30, 2023) Report from the Director, Traffic Management, Transportation Services

Summary

This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision.

 

First Gulf is constructing a 24-storey office building at 25 Ontario Street.  The site is located on the southeast corner of Adelaide Street East and Ontario Street.  The east sidewalk and a 3.3 metre wide portion of the most easterly curb lane on Ontario Street is currently closed to accommodate a construction staging area. Toronto and East York Community Council at its meeting on May 19, 2021, approved an extension for the subject staging area on Ontario Street from July 1, 2021 to December 31, 2022.  The developer has experienced delays due to COVID-19, supply chain issues, inclement weather, and various sub-trade union strikes that have delayed the completion of the project until April 30, 2024.

 

Transportation Services is requesting authorization to extend the duration of the construction staging area for an additional eight months (i.e. September 20, 2023 to April 30, 2024) to allow for the construction of the development to be completed.

Background Information

(August 30, 2023) Report and Attachment 1 from the Director, Traffic Management, Transportation Services on Construction Staging Area Time Extension - 25 Ontario Street
https://www.toronto.ca/legdocs/mmis/2023/te/bgrd/backgroundfile-238894.pdf

Motions

1 - Motion to Amend Item moved by Councillor Chris Moise (Carried)

That Toronto and East York Community Council amend Recommendation 2 by adding the words "and pressure wash" so that it now reads as follows: 

 

2. Toronto and East York Community Council direct the applicant to continue to sweep and pressure wash the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe.


Motion to Adopt Item as Amended moved by Councillor Chris Moise (Carried)