Item - 2023.EX8.2
Tracking Status
- City Council adopted this item on October 11 and 12, 2023 without amendments.
- This item was considered by the Executive Committee on October 3, 2023 and adopted without amendment. It will be considered by City Council on October 11 and 12, 2023.
EX8.2 - Capital Variance Report for the Six months Ended June 30, 2023
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
City Council Decision
City Council on October 11 and 12, 2023, adopted the following:
1. City Council approve in-year budget adjustments to the 2023-2032 Capital Budget and Plan as detailed in Appendix 4 to the report (September 18, 2023) from the Interim Chief Financial Officer and Treasurer.
Background Information (Committee)
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-239368.pdf
Appendix 1 - 2023 Capital Variance Summary for the Six months Ended June 30, 2023
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-239389.pdf
Appendix 2A - 2023 Q2 Capital Projects Recommended for Full Closure
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-239390.pdf
Appendix 2B - 2023 Q2 Capital Projects Recommended for Partial Closure
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-239391.pdf
Appendix 3 - 2023 Q2 Major Capital Projects
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-239392.pdf
Appendix 4 - In-Year Adjustments for the Six months Ended June 30, 2023
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-239393.pdf
Appendix 5 - 2023 Q2 Capital Variance Dashboard by Program and Agency
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-239394.pdf
Motions (City Council)
EX8.2 - Capital Variance Report for the Six months Ended June 30, 2023
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
Committee Recommendations
The Executive Committee recommends that:
1. City Council approve in-year budget adjustments to the 2023-2032 Adopted Capital Budget and Plan as detailed in Appendix 4 to the report (September 18, 2023) from the Interim Chief Financial Officer and Treasurer.
Origin
Summary
The purpose of this report is to provide City Council with the City of Toronto capital spending for the Six months period ended June 30, 2023, as well as the year-end projected expenditures to December 31, 2023. Furthermore, this report seeks Council's approval for in-year budget adjustments to the 2023 Adopted Capital Budget and Plan.
Table 1 below summarizes the City's 2023 actual capital expenditures compared with the 2023 approved capital budget for the Six months period ended June 30, 2023 and the projected expenditures by December 31, 2023.
Table 1: Capital Variance Summary
|
Table 1 |
|||||
|
Corporate Capital Variance Summary |
|||||
|
for the Period Ended June 30, 2023 |
|||||
|
|
2023 Approved Budget* |
2023 Q2 Actual |
2023 Projected |
||
|
|
$M |
$M |
% |
$M |
% |
|
City Operations |
2,651.6 |
658.1 |
24.8% |
1,963.6 |
74.1% |
|
Agencies |
1,735.3 |
541.2 |
31.2% |
1,554.7 |
89.6% |
|
Tax Supported: |
4,386.9 |
1,199.3 |
27.3% |
3,518.3 |
80.2% |
|
Rate Supported: |
1,562.3 |
378.7 |
24.2% |
1,318.0 |
84.4% |
|
TOTAL |
5,949.2 |
1,578.1 |
26.5% |
4,836.3 |
81.3% |
|
*Note: Includes 2022 carry forward funding |
|||||
The City's actual capital spending through the first six months of 2023 is $1.578 billion or 26.5% of the Adopted Capital budget of the year. The projected spending rate is 81.3% by year-end based on submissions from City Programs and Agencies.
Background Information
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-239368.pdf
Appendix 1 - 2023 Capital Variance Summary for the Six months Ended June 30, 2023
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-239389.pdf
Appendix 2A - 2023 Q2 Capital Projects Recommended for Full Closure
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-239390.pdf
Appendix 2B - 2023 Q2 Capital Projects Recommended for Partial Closure
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-239391.pdf
Appendix 3 - 2023 Q2 Major Capital Projects
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-239392.pdf
Appendix 4 - In-Year Adjustments for the Six months Ended June 30, 2023
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-239393.pdf
Appendix 5 - 2023 Q2 Capital Variance Dashboard by Program and Agency
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-239394.pdf