Item - 2023.EX6.5
Tracking Status
- City Council adopted this item on July 19 and 20, 2023 without amendments and without debate.
- This item was considered by the Executive Committee on July 11, 2023 and adopted without amendment. It will be considered by City Council on July 19 and 20, 2023.
EX6.5 - Capital Variance Report for the Four months Ended April 30, 2023
- Decision Type:
- ACTION
- Status:
- Adopted on Consent
- Wards:
- All
City Council Decision
City Council on July 19 and 20, 2023, adopted the following:
1. City Council approve in-year budget adjustments to the 2023-2032 Adopted Capital Budget and Plan as detailed in Appendix 4 to the report (June 26, 2023) from the Chief Financial Officer and Treasurer.
Background Information (Committee)
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-237919.pdf
Appendix 1 - 2023 Capital Variance Summary for the Four months Ended April 30, 2023
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-237920.pdf
Appendix 2 - 2023 4M Capital Projects Recommended for Full Closure
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-237921.pdf
Appendix 3 - 2023 4M Major Capital Projects
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-237922.pdf
Appendix 4 - In-Year Adjustments for the Four months Ended April 30, 2023
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-237923.pdf
Appendix 5 - 2023 4M Capital Variance Dashboard by Program and Agency
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-237924.pdf
EX6.5 - Capital Variance Report for the Four months Ended April 30, 2023
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
Committee Recommendations
The Executive Committee recommends that:
1. City Council approve in-year budget adjustments to the 2023-2032 Adopted Capital Budget and Plan as detailed in Appendix 4 to the report (June 26, 2023) from the Chief Financial Officer and Treasurer.
Origin
Summary
The purpose of this report is to provide City Council with the City of Toronto capital spending for the four month period ended April 30, 2023, as well as projected expenditures to December 31, 2023. Furthermore, this report seeks Council's approval for in-year budget adjustments to the 2023 Adopted Capital Budget and Plan.
Table 1 below summarizes the City's 2023 actual capital expenditures compared with the 2023 approved capital budget for the period ended April 30, 2023 as well as the projected expenditures by December 31, 2023.
Table 1: Capital Variance Summary
|
Table 1 |
|||||
|
Corporate Capital Variance Summary |
|||||
|
for the Period Ended April 30, 2023 |
|||||
|
|
2023 Adopted Budget* |
2023 4M Actual |
2023 Projected |
||
|
|
$M |
$M |
% |
$M |
% |
|
City Operations |
2,634.4 |
399.4 |
15.2% |
2,181.1 |
82.8% |
|
Agencies |
1,734.2 |
256.1 |
14.8% |
1,585.0 |
91.4% |
|
Tax Supported: |
4,368.6 |
655.5 |
15.0% |
3,766.1 |
86.2% |
|
Rate Supported: |
1,562.3 |
197.0 |
12.6% |
1,349.0 |
86.4% |
|
TOTAL |
5,930.9 |
852.5 |
14.4% |
5,115.2 |
86.2% |
|
*Note: Includes 2022 carry forward funding |
|||||
The City's actual capital spending through the first four months of 2023 is $852.5 million or 14.4% of the adopted capital budget of the year. The projected spending rate is 86.2% by year-end based on submissions from City divisions and agencies.
Background Information
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-237919.pdf
Appendix 1 - 2023 Capital Variance Summary for the Four months Ended April 30, 2023
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-237920.pdf
Appendix 2 - 2023 4M Capital Projects Recommended for Full Closure
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-237921.pdf
Appendix 3 - 2023 4M Major Capital Projects
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-237922.pdf
Appendix 4 - In-Year Adjustments for the Four months Ended April 30, 2023
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-237923.pdf
Appendix 5 - 2023 4M Capital Variance Dashboard by Program and Agency
https://www.toronto.ca/legdocs/mmis/2023/ex/bgrd/backgroundfile-237924.pdf