Item - 2023.BA42.6
Tracking Status
- This item was considered by Bid Award Panel on August 23, 2023 and was adopted without amendment.
BA42.6 - Award of Ariba Document Number 4031969151 to Pegah Construction Ltd., for the Construction of a New Pre-Engineered Fabric and Metal Salt Storage Structure for Transportation Services
- Decision Type:
- ACTION
- Status:
- Adopted
- Ward:
- 8 - Eglinton - Lawrence
Panel Decision
The Bid Award Panel adopted the following:
1. Bid Award Panel grant authority to award the contract in accordance with the Contract Details set out in the report (August 17, 2023) from the Chief Procurement Officer:
Solicitation Number:
Request for Tender, Ariba Document Number 4031969151, Contract Number 23TR-OM-001-TEY-WE
Description:
For Construction of a New Pre-Engineered Fabric and Metal Salt Storage Structure including Excavation of Yard, Construction of Foundation, Slab on Grade and Base Walls - 1401 Castlefield Avenue
Recommended Supplier:
Pegah Construction Ltd.
Contract Award Value:
$2,277,888 net of all applicable taxes and charges
$2,574,013 including HST and all applicable charges
$2,317,978 net of HST recoveries
Contract is expected to start on the date of award and end on December 31, 2023.
Origin
Summary
Solicitation Issued: June 15, 2023 Solicitation Closed: July 18, 2023
Number of Addenda Issued: Four (4)
Number of Bids: Eight (8)
Table 2: Summary of Bids Received
|
Supplier Name |
Bid Price (excluding H.S.T.) |
|
Pegah Construction Ltd. |
$2,127,887.50 * |
|
Alliance Verdi Civil Inc. |
$2,273,474.00 |
|
1568796 Ontario Inc., O/A Renokrew |
$2,292,893.86 |
|
Canada Construction Ltd. |
$2,830,411.60 |
|
Pine Valley Corporation |
$3,149,291.40 |
|
Greenspace Construction Inc. |
$3,165,643.39 |
|
Martinway Contracting Ltd. |
$4,322,448.00 |
|
South Central Inc. |
$4,838,741.00 |
* Pursuant to the Request for Tender document the contract award value includes contingency.
Background Information
https://www.toronto.ca/legdocs/mmis/2023/ba/bgrd/backgroundfile-238666.pdf
Motions
Moved by Lena Dianda.
Vote (Adopt Item)
|
Result: |
Majority Required |
|
Yes: |
Leah Ross (Chair), Diana Santucci, Lena Dianda |
|
No: |
|
|
Absent: |
David McLeod |