Item - 2023.BA30.7
Tracking Status
- This item was considered by Bid Award Panel on June 7, 2023 and was adopted without amendment.
BA30.7 - Award of Ariba Document Number 3892675887 to Fer-Pal Construction Ltd., for Watermain Cured-in-Place-Pipe Lining in Etobicoke York District for Toronto Water
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- 1 - Etobicoke North, 7 - Humber River - Black Creek
Panel Decision
The Bid Award Panel adopted the following:
1. Bid Award Panel grant authority to award the contract in accordance with the Contract Details set out in the report (June 1, 2023) from the Chief Procurement Officer:
Solicitation Number:
Request for Tender, Ariba Document Number 3892675887, Contract Number 23TW-CTS-01CWD.
Description:
Watermain Cured-in-Place-Pipe Lining Lining in Etobicoke York District, Wards 1 and 7.
Recommended Supplier:
Fer-Pal Construction Ltd.
Contract Award Value:
$15,397,908 net of all applicable taxes and charges
$17,399,636 including HST and all applicable charges
$15,668,911 net of HST recoveries
Contract is expected to start on date of award and end on December 31, 2025.
Origin
Summary
Solicitation Issued: March 3, 2023 Solicitation Closed: April 14, 2023
Number of Addenda Issued: Two (2)
Number of Bids: Two (2)
Table 2: Summary of Bids Received including bid price
|
Supplier Name |
Bid Price (excluding H.S.T.) |
|
Fer-Pal Construction Ltd. |
$13,998,098.00* |
|
Robert B. Somerville Co. Limited |
$14,618,269.00 |
* Pursuant to the Request for Tender document the contract award value includes contingency.
Background Information
https://www.toronto.ca/legdocs/mmis/2023/ba/bgrd/backgroundfile-236945.pdf
Motions
Moved by Lena Dianda.
Vote (Adopt Item)
|
Result: |
Majority Required |
|
Yes: |
Leah Ross (Chair), David McLeod, Diana Santucci, Lena Dianda |
|
No: |
|
|
Absent: |
|