Item - 2023.AU3.10

Tracking Status

  • City Council adopted this item on December 13, 14 and 15, 2023 without amendments and without debate.
  • This item was considered by the Audit Committee on December 1, 2023 and adopted without amendment. It will be considered by City Council on December 13, 14 and 15, 2023.

AU3.10 - Community Centres - 2022 Audited Financial Statements (Report 2)

Decision Type:
ACTION
Status:
Adopted on Consent
Wards:
All

City Council Decision

City Council on December 13, 14, and 15, 2023, adopted the following:

 

1. City Council receive the 2022 audited financial statements and management letters, where applicable, for the Community Centres in Attachments 1 and 2 to the report (November 15, 2023) from the Auditor General for information.

Background Information (Committee)

(November 15, 2023) Report from the Auditor General on Community Centres - 2022 Audited Financial Statements
https://www.toronto.ca/legdocs/mmis/2023/au/bgrd/backgroundfile-240775.pdf
(November 15, 2023) Attachment 1: Financial Statements and Report to the Board of Management - Applegrove Community Complex
https://www.toronto.ca/legdocs/mmis/2023/au/bgrd/backgroundfile-240789.pdf
(November 15, 2023) Attachment 2: Financial Statements - Scadding Court Community Centre
https://www.toronto.ca/legdocs/mmis/2023/au/bgrd/backgroundfile-240790.pdf

AU3.10 - Community Centres - 2022 Audited Financial Statements (Report 2)

Decision Type:
ACTION
Status:
Adopted
Wards:
All

Committee Recommendations

The Audit Committee recommend that:

 

1. City Council receive the 2022 audited financial statements and management letters, where applicable, for the Community Centres in attachments 1 and 2 to the report (November 15, 2023) from the Auditor General for information.

Origin

(November 15, 2023) Report from the Auditor General

Summary

The purpose of this report is to provide the Audit Committee and City Council with the 2022 audited financial statements of Community Centres.

 

The 2022 audited financial statements for the 10 Community Centres are presented to Audit Committee after approval by their respective Boards of Management.

 

Of the 10 City Community Centres, the audited financial statements for eight Community Centres were previously presented at the July 7, 2023 meeting of the Audit Committee. At this time, the audits of the remaining two Community Centres have been completed.  

 

This report presents the 2022 Independent Auditor's Reports, accompanying financial statements and management control letters (where applicable) for Applegrove Community Complex and Scadding Court Community Centre.

Background Information

(November 15, 2023) Report from the Auditor General on Community Centres - 2022 Audited Financial Statements
https://www.toronto.ca/legdocs/mmis/2023/au/bgrd/backgroundfile-240775.pdf
(November 15, 2023) Attachment 1: Financial Statements and Report to the Board of Management - Applegrove Community Complex
https://www.toronto.ca/legdocs/mmis/2023/au/bgrd/backgroundfile-240789.pdf
(November 15, 2023) Attachment 2: Financial Statements - Scadding Court Community Centre
https://www.toronto.ca/legdocs/mmis/2023/au/bgrd/backgroundfile-240790.pdf

Motions

Motion to Adopt Item moved by Councillor Jamaal Myers (Carried)
Source: Toronto City Clerk at www.toronto.ca/council