Item - 2022.TE32.50

Tracking Status

  • City Council adopted this item on May 11 and 12, 2022 without amendments and without debate.
  • This item was considered by the Toronto and East York Community Council on April 21, 2022 and adopted without amendment. It will be considered by City Council on May 11 and 12, 2022.

TE32.50 - Construction Staging Area - Time Extension - Port Lands Flood Protection - Cherry Street Temporary Diversion Road

Decision Type:
ACTION
Status:
Adopted on Consent
Ward:
14 - Toronto - Danforth

City Council Decision

City Council on May 11 and 12, 2022, adopted the following:

 

1. City Council authorize the continuation of the temporary closure to vehicular and pedestrian traffic on the west sidewalk and two southbound lanes on Cherry Street between a point 55 metres south of Commissioners Street and a point 393.5 metres further south, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project.

 

2. City Council authorize the continuation of the temporary closure to pedestrian traffic on the east sidewalk on Cherry Street, between a point 195 metres south of Commissioners Street and a point 263 metres further south, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project.

 

3. City Council authorize the continuation of the temporary closure to pedestrian and cycling traffic Martin Goodman Trail on the east side of Cherry Street, between a point 195 metres south of Commissioners Street and a point 263 metres further south, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project.

 

4. City Council authorize the continuation of the temporary closure to vehicular and pedestrian traffic each of the north boulevard and the 5.5 metre wide portion of the westbound lane on Polson Street, between Cherry Street and a point 83.5 metres west, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project.

 

5. City Council direct that Waterfront Toronto continue to be responsible for all costs incurred with respect to road repairs and traffic signage modifications.

Background Information (Community Council)

(April 1, 2022) Report and Attachment from the Director, Traffic Management, Transportation Services - Construction Staging Area - Time Extension - Port Lands Flood Protection - Cherry Street Temporary Diversion Road
https://www.toronto.ca/legdocs/mmis/2022/te/bgrd/backgroundfile-223927.pdf

TE32.50 - Construction Staging Area - Time Extension - Port Lands Flood Protection - Cherry Street Temporary Diversion Road

Decision Type:
ACTION
Status:
Adopted
Ward:
14 - Toronto - Danforth

Community Council Recommendations

The Toronto and East York Community Council:

 

1. City Council authorize the continuation of the temporary closure to vehicular and pedestrian traffic on the west sidewalk and two southbound lanes on Cherry Street between a point 55 metres south of Commissioners Street and a point 393.5 metres further south, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project.

 

2. City Council authorize the continuation of the temporary closure to pedestrian traffic on the east sidewalk on Cherry Street, between a point 195 metres south of Commissioners Street and a point 263 metres further south, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project.

 

3. City Council authorize the continuation of the temporary closure to pedestrian and cycling traffic Martin Goodman Trail on the east side of Cherry Street, between a point 195 metres south of Commissioners Street and a point 263 metres further south, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project.

 

4. City Council authorize the continuation of the temporary closure to vehicular and pedestrian traffic each of the north boulevard and the 5.5 metre wide portion of the westbound lane on Polson Street, between Cherry Street and a point 83.5 metres west, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project.

 

5. City Council direct that Waterfront Toronto continue to be responsible for all costs incurred with respect to road repairs and traffic signage modifications.

Origin

(April 1, 2022) Report from the Director, Traffic Management, Transportation Services

Summary

As the Toronto Transit Commission (TTC) operates a transit service on Cherry Street, City Council approval of this report is required.

 

As part of the Port Lands Flood Protection Project and Enabling Infrastructure Project, Waterfront Toronto has undertaken the construction of the Cherry Street re-alignment, between Lake Shore Boulevard East and Polson Street. A construction staging area has been set-up on the west side of Cherry Street and the north side of Polson Street.

In addition, a temporary detour (diversion) roadway has been fully constructed within the existing northbound lanes, east boulevard on Cherry Street, and within the additional lands on the east side of Cherry Street (leased from City of Toronto Economic Development Corporation) to accommodate northbound and southbound traffic around the construction staging area.

 

City Council, at its meeting on May 28, 2020, authorized the subject construction staging area on Cherry Street, from June 29, 2020 to February 28, 2022. At the time, Waterfront Toronto indicated they would require the construction staging area for a total of 34 months. At its meetings on February 2, 2022, City Council subsequently authorized extending the duration of the construction staging area until May 31, 2022.

 

Waterfront Toronto has requested an extension of the duration of the construction staging area on Cherry Street, in order to complete the construction of the Cherry Street re-alignment. Based on the information provided by Waterfront Toronto, the site has experienced additional construction delays due to dewatering challenges.

 

Transportation Services is requesting authorization to extend the duration of the construction staging area and temporary detour (diversion) roadway until July 31, 2022 in order to complete the construction of the re-alignment.

Background Information

(April 1, 2022) Report and Attachment from the Director, Traffic Management, Transportation Services - Construction Staging Area - Time Extension - Port Lands Flood Protection - Cherry Street Temporary Diversion Road
https://www.toronto.ca/legdocs/mmis/2022/te/bgrd/backgroundfile-223927.pdf

Motions

1 - Motion to Adopt Item moved by Councillor Paula Fletcher (Carried)
Source: Toronto City Clerk at www.toronto.ca/council