Item - 2022.TE32.49

Tracking Status

  • City Council adopted this item on May 11 and 12, 2022 without amendments and without debate.
  • This item was considered by Toronto and East York Community Council on April 21, 2022 and was adopted with amendments. It will be considered by City Council on May 11 and 12, 2022.

TE32.49 - Construction Staging Area Time Extension - 6-16 Wellesley Street West and 5-7 St. Nicholas Street

Decision Type:
ACTION
Status:
Adopted on Consent
Ward:
13 - Toronto Centre

City Council Decision

City Council on May 11 and 12, 2022, adopted the following:

 

1. City Council authorize the continuation of the closure of the north sidewalk and a 2.3-metre-wide portion of the westbound curb lane on Wellesley Street West, between Bistro Lane and St. Nicholas Street, and provision of a temporary pedestrian walkway within the closed portion of the eastbound curb lane from July 1, 2022 to June 30, 2023.
 

2. City Council authorize the continuation of the closure of all of St. Nicholas Street, between Wellesley Street West and a point 43 metres north, from July 1, 2022 to June 30, 2023.

 

3. City Council direct the applicant to pressure wash (or sweep during winter weather conditions) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe.

 

4. City Council direct the applicant to continue ensuring that the existing sidewalks or the proposed pedestrian walkways have proper enhanced lighting to ensure safety and visibility at all times of the day and night.

 

5. City Council direct the applicant to continue consulting and communicating all construction, parking and road occupancy impacts with local Business Improvement Areas and resident associations in advance of any physical road modifications.

 

6. City Council direct the applicant to continue installing appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times.

 

7. City Council direct the applicant to continue providing a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and the Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public.

 

8. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and the Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public.

 

9. City Council direct the applicant to continue installing cane detection within the covered and protected walkway to guide pedestrians who are visually impaired.

 

10. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

11. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.

 

12. City Council direct the applicant to continue construction management working group monthly meetings, and inviting local stakeholders including Transportation Services, Municipal Licensing and Standards, Toronto Buildings, adjacent neighbours and local resident groups.
 

13. City Council direct that Wellesley Street West and St. Nicholas Street be returned to its pre-construction traffic and parking regulations when the project is complete.

 

14. City Council direct the applicant to create a publicly accessible website with regular construction updates and post the website address on the construction site hoarding, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.


15. City Council direct the applicant to sweep the construction site daily and nightly, or more frequently as needed to be cleared of any construction debris and made safe.


16. City Council direct the applicant to mitigate light pollution by installing a shield/barrier on any lighting standards in close proximity to adjacent residential properties, such as cranes.


17. City Council direct the applicant, in consultation with Transportation Services, to maintain any bike lanes, install sharrow markings onto the roadway, and display appropriate signage to inform drivers and cyclists to safely share the road.


18. City Council direct the applicant to email monthly construction progress reports to the local Councillor, local residents’ association and Business Improvement Area Board of Management.

Background Information (Community Council)

(April 1, 2022) Report and Attachment from the Director, Traffic Management, Transportation Services - Construction Staging Area Time Extension - 6-16 Wellesley Street West and 5-7 St. Nicholas Street
https://www.toronto.ca/legdocs/mmis/2022/te/bgrd/backgroundfile-223946.pdf

Communications (Community Council)

(April 18, 2022) Letter from Jack Candido, President, Bay Cloverhill Community Association (TE.Supp)
https://www.toronto.ca/legdocs/mmis/2022/te/comm/communicationfile-148876.pdf

TE32.49 - Construction Staging Area Time Extension - 6-16 Wellesley Street West and 5-7 St. Nicholas Street

Decision Type:
ACTION
Status:
Amended
Ward:
13 - Toronto Centre

Community Council Recommendations

The Toronto and East York Community Council recommends that:

 

1. City Council authorize the continuation of the closure of the north sidewalk and a 2.3-metre-wide portion of the westbound curb lane on Wellesley Street West, between Bistro Lane and St. Nicholas Street, and provision of a temporary pedestrian walkway within the closed portion of the eastbound curb lane from July 1, 2022 to June 30, 2023.
 

2. City Council authorize the continuation of the closure of all of St. Nicholas Street, between Wellesley Street West and a point 43 metres north, from July 1, 2022 to
June 30, 2023.

 

3. City Council direct the applicant to pressure wash (or sweep during winter weather conditions) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe.

 

4. City Council direct the applicant to continue ensuring that the existing sidewalks or the proposed pedestrian walkways have proper enhanced lighting to ensure safety and visibility at all times of the day and night.

 

5. City Council direct the applicant to continue consulting and communicating all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications.

 

6. City Council direct the applicant to continue installing appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times.

 

7. City Council direct the applicant to continue providing a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public.

 

8. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public.

 

9. City Council direct the applicant to continue installing cane detection within the covered and protected walkway to guide pedestrians who are visually impaired.

 

10. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

11. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.

 

12. City Council direct the applicant to continue construction management working group monthly meetings, and inviting local stakeholders including Transportation Services, Municipal Licensing and Standards, Toronto Buildings, adjacent neighbours, and local resident groups.
 

13. City Council direct that Wellesley Street West and St. Nicholas Street be returned to its pre-construction traffic and parking regulations when the project is complete.

 

14. City Council direct the applicant to create a publicly accessible website with regular construction updates and post the website address on the construction site hoarding, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.


15. City Council direct the applicant to sweep the construction site daily and nightly, or more frequently as needed to be cleared of any construction debris and made safe.


16. City Council direct the applicant to mitigate light pollution by installing a shield/barrier on any lighting standards in close proximity to adjacent residential properties, such as cranes.


17. City Council direct the applicant, in consultation with Transportation Services, to maintain any bike lanes, install sharrow markings onto the roadway, and display appropriate signage to inform drivers and cyclists to safely share the road.


18. City Council direct the applicant to email monthly construction progress reports to the local Councillor, local residents’ association, and Business Improvement Area Board of Management.

Origin

(April 1, 2022) Report from the Director, Traffic Management, Transportation Services

Summary

As the Toronto Transit Commission (TTC) operates a transit service on Wellesley Street West, City Council approval of this report is required. In addition, this report proposes extending the duration of the temporary removal of the cycle track on the north side of Wellesley Street West abutting the development. Based on these conditions, this matter requires final approval by City Council.

 

Wellesley Street Nicholas Residences Limited Partnership is constructing a 55-storey residential development building at 6-16 Wellesley Street West and 5-7 St. Nicholas Street. The site is located on the north side of Wellesley Street West, west of Yonge Street between Bistro Lane and St. Nickolas Street. The north sidewalk and a 2.3-metre-wide portion of the westbound curb lane/cycle track on Wellesley Street West, between Bistro Lane and St. Nicholas Street is currently closed to accommodate construction staging operations for the development. In addition, St. Nicholas Street is closed in its entirety, between Wellesley Street West and a point 43 metres north.

 

City Council, at its meeting on June 8, 2021, approved the subject construction staging areas from July 1, 2021 to June 30, 2022. At the time, the developer indicated they would require the staging area for a total of 54 months, from July 1, 2021 to December 31, 2025.

 

As the previous permit was only approved for a 12-month period, the developer has requested an extension of the duration of the construction staging areas on Wellesley Street West and St. Nicholas Street in order to complete the construction of the development.

 

Transportation Services is requesting authorization to extend the duration of the construction staging areas on Wellesley Street West and St. Nicholas Street for an additional 31 months, from July 1, 2022 to January 31, 2025, to allow for the construction of the development to be completed.

Background Information

(April 1, 2022) Report and Attachment from the Director, Traffic Management, Transportation Services - Construction Staging Area Time Extension - 6-16 Wellesley Street West and 5-7 St. Nicholas Street
https://www.toronto.ca/legdocs/mmis/2022/te/bgrd/backgroundfile-223946.pdf

Communications

(April 18, 2022) Letter from Jack Candido, President, Bay Cloverhill Community Association (TE.Supp)
https://www.toronto.ca/legdocs/mmis/2022/te/comm/communicationfile-148876.pdf

Motions

1 - Motion to Amend Item (Additional) moved by Councillor Kristyn Wong-Tam (Carried)

That:

 

1. Recommendations 1 and 2 be deleted and replaced with the following new recommendations:

 

1. City Council authorize the continuation of the closure of the north sidewalk and a 2.3-metre-wide portion of the westbound curb lane on Wellesley Street West, between Bistro Lane and St. Nicholas Street, and provision of a temporary pedestrian walkway within the closed portion of the eastbound curb lane from July 1, 2022 to June 30, 2023.
 

2. City Council authorize the continuation of the closure of all of St. Nicholas Street, between Wellesley Street West and a point 43 metres north, from July 1, 2022 to
June 30, 2023.

 

2. The following new recommendations be added:

 

14. Direct the applicant to create a publicly accessible website with regular construction updates and post the website address on the construction site hoarding, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.


15. Direct the applicant to sweep the construction site daily and nightly, or more frequently as needed to be cleared of any construction debris and made safe.


16. Direct the applicant to mitigate light pollution by installing a shield/barrier on any lighting standards in close proximity to adjacent residential properties, such as cranes.


17. Direct the applicant, in consultation with Transportation Services, to maintain any bike lanes, install sharrow markings onto the roadway, and display appropriate signage to inform drivers and cyclists to safely share the road.


18. Direct the applicant to email monthly construction progress reports to the local Councillor, local residents’ association, and Business Improvement Area Board of Management.


2 - Motion to Adopt Item as Amended moved by Councillor Gord Perks (Carried)
Source: Toronto City Clerk at www.toronto.ca/council