Item - 2022.TE32.24

Tracking Status

  • This item was considered by Toronto and East York Community Council on April 21, 2022 and was adopted without amendment. City Council has delegated authority for this matter to the Toronto and East York Community Council and therefore, the decision is final.

TE32.24 - Ontario Line Joint Corridor - Early Works Construction and Right-of-Way Permits

Decision Type:
ACTION
Status:
Adopted
Schedule Type:
Delegated
Ward:
14 - Toronto - Danforth

Community Council Decision

The Toronto and East York Community Council: 

 

1. Received the report (April 1, 2022) from the Director, Planning and Capital Program, Transportation Services, and the supplementary report (April 20, 2022) from the General Manager, Parks, Forestry and Recreation, for information.

Origin

(April 1, 2022) Report from the Director, Planning and Capital Program, Transportation Services

Summary

As part of the approval for Item MM41.16, City Council requested a report on Metrolinx's Ontario Line construction work, access routes, traffic mitigation measures, permit conditions, and a mechanism to review right-of-way permits for the Ontario Line project in Ward 14.

 

This report provides an overview of Metrolinx's construction proposal for Early Works in the Lakeshore East Joint Corridor and discusses its construction impacts and mitigation measures. Additionally, the report discusses the City's permit process and requirements.

Background Information

(April 1, 2022) Report form the Director, Planning and Capital Program, Transportation Services - Ontario Line Joint Corridor - Early Works Construction and Right-of-Way Permits
https://www.toronto.ca/legdocs/mmis/2022/te/bgrd/backgroundfile-223941.pdf

Communications

(April 19, 2022) E-mail from Michael Holloway (TE.Supp)

Motions

1 - Motion to Amend Item moved by Councillor Gord Perks (Carried)

The the report (April 20, 2022) from the General Manager, Parks, Forestry and Recreation, be received for information.


2 - Motion to Adopt Item as Amended moved by Councillor Paula Fletcher (Carried)

24a - Supplementary Report - Ontario Line Joint Corridor - Early Works Construction and Right-of-Way Permits

Origin
(April 20, 2022) Report from the General Manager, Parks, Forestry and Recreation
Summary

At the March 9, 2022 meeting of City Council, Parks, Forestry and Recreation was directed to report to the Toronto and East York Community Council meeting of April 21, 2022 on proposals for a mechanism to review any and all tree removal proposals or permits in the vicinity of the Ontario Line project in Toronto-Danforth (Ward 14). The purpose of this report is to provide an overview of the notification process for tree permits associated with Metrolinx's Ontario Line project.

 

Background Information
(April 20, 2022) Report from the General Manager, Parks, Forestry and Recreation - Supplementary Report - Ontario Line Joint Corridor - Early Works Construction and Right-of-Way Permits
https://www.toronto.ca/legdocs/mmis/2022/te/bgrd/backgroundfile-224746.pdf
Source: Toronto City Clerk at www.toronto.ca/council