Item - 2022.EY31.15

Tracking Status

  • City Council adopted this item on May 11 and 12, 2022 without amendments and without debate.
  • This item was considered by Etobicoke York Community Council on April 19, 2022 and was adopted with amendments. It will be considered by City Council on May 11 and 12, 2022.
  • See also By-law 409-2022

EY31.15 - Temporary Road Closing of Islington Avenue and Parking Regulation Amendments - 2022 Canadian Open

Decision Type:
ACTION
Status:
Adopted on Consent
Ward:
2 - Etobicoke Centre

City Council Decision

City Council on May 11 and 12, 2022, adopted the following:

 

1. City Council receive Attachment 1, 2022 RBC Canadian Open Transportation Management Plan, to the report (March 30, 2022) from the Director, Traffic Management, Transportation Services.

 

2. City Council authorize the closing of Islington Avenue to traffic from Eglinton Avenue West to The Kingsway, for the period from May 30, 2022 to June 17, 2022.

 

3. City Council amend Appendix A to the report (March 30, 2022) from the Director, Traffic Management, Transportation Services so that it is better aligned with the Map of Appendix B, by removing the following streets:

 

a. Abinger Crescent;

 

b. Appledale Road;

 

c. Ashford Drive; and

 

d. North Heights Road.

 

4. City Council authorize the temporary parking, stopping and standing regulations on streets in the vicinity of St. George's Golf and Country Club, identified in Appendix A attached to the report (March 30, 2022) from the Director, Traffic Management, Transportation Services, and as amended by Part 3 above.

 

5. City Council direct that all costs associated with the road closings, including the costs of restoring and cleaning the streets following each event, as well as installing/removing temporary parking restrictions, shall be completed by Golf Canada to the satisfaction of Transportation Services, and at no cost to the City.

 

6. City Council authorize the temporary use of the Hydro One right-of-way, east of Martin Grove Drive between Hedges Boulevard and Princess Margaret Boulevard, by Golf Canada for media and supplier parking, subject to approval by Hydro One, subject to access and permit approval from Transportation Services, Permits and Enforcement and at no cost to the City, for the period from May 30, 2022 to June 17, 2022.

Background Information (Community Council)

(March 30, 2022) Report and Appendix A and B from the Director, Traffic Management, Transportation Services on Temporary Road Closing of Islington Avenue and Parking Regulation Amendments - 2022 Canadian Open
https://www.toronto.ca/legdocs/mmis/2022/ey/bgrd/backgroundfile-223297.pdf
Attachment 1: 2022 RBC Canadian Open Transportation Management Plan
https://www.toronto.ca/legdocs/mmis/2022/ey/bgrd/backgroundfile-223418.pdf

EY31.15 - Temporary Road Closing of Islington Avenue and Parking Regulation Amendments - 2022 Canadian Open

Decision Type:
ACTION
Status:
Amended
Ward:
2 - Etobicoke Centre

Community Council Recommendations

The Etobicoke York Community Council recommends that:

 

1. City Council receive Attachment 1, 2022 RBC Canadian Open Transportation Management Plan, to the report (March 30, 2022) from the Director, Traffic Management, Transportation Services.

 

2. City Council authorize the closing of Islington Avenue to traffic from Eglinton Avenue West to The Kingsway, for the period from May 30, 2022 to June 17, 2022.

 

3. City Council amend Appendix A to the report (March 30, 2022) from the Director, Traffic Management, Transportation Services so that it is better aligned with the Map of Appendix B, by removing the following streets:

 

a. Abinger Crescent

b. Appledale Road

c. Ashford Drive

d. North Heights Road

 

4. City Council authorize the temporary parking, stopping and standing regulations on streets in the vicinity of St. George's Golf and Country Club, identified in Appendix "A" attached to the report (March 30, 2022) from the Director, Traffic Management, Transportation Services, and as amended by Recommendation 3 above.

 

5. City Council direct that all costs associated with the road closings, including the costs of restoring and cleaning the streets following each event, as well as installing/removing temporary parking restrictions, shall be completed by Golf Canada to the satisfaction of Transportation Services, and at no cost to the City.

 

6. City Council authorize the temporary use of the Hydro One right-of-way, east of Martin Grove Drive between Hedges Boulevard and Princess Margaret Boulevard, by Golf Canada for media and supplier parking, subject to approval by Hydro One, subject to access and permit approval from Transportation Services, Permits and Enforcement and at no cost to the City, for the period from May 30, 2022 to June 17, 2022.

Origin

(March 30, 2022) Report from the Director, Traffic Management, Transportation Services

Summary

As the Toronto Transit Commission (TTC) operates bus service on Islington Avenue, City Council approval of this report is required.

 

The purpose of this report is to present the Traffic Management Plan prepared by

IBI Group on behalf of Golf Canada, relating to the full closure of Islington Avenue, between Eglinton Avenue West and The Kingsway, for a period up to 19 days, from Monday May 30, 2022, to Friday, June 17, 2022. The closing is required as Golf Canada is hosting the 2022 Canadian Open at St. George's Golf and Country Club, located on Islington Avenue, between the intersections of Ridge Valley Crescent/Prince George Drive and Princess Margaret Boulevard/Poplar Heights Drive. The closing includes the Pre-tournament (May 30, 2022 to June 5, 2022), Tournament (June 6, 2022 to June 12, 2022) and the Post-tournament (June 13, 2022 to June 17, 2022) events.

 

This report also recommends implementing temporary parking, standing and stopping regulations during the Tournament week (June 6, 2022 to June 12, 2022) on streets in the vicinity of the golf club and the visitor parking areas.

 

The Toronto Transit Commission has been consulted and has no concerns regarding the proposals contained in this report.

Background Information

(March 30, 2022) Report and Appendix A and B from the Director, Traffic Management, Transportation Services on Temporary Road Closing of Islington Avenue and Parking Regulation Amendments - 2022 Canadian Open
https://www.toronto.ca/legdocs/mmis/2022/ey/bgrd/backgroundfile-223297.pdf
Attachment 1: 2022 RBC Canadian Open Transportation Management Plan
https://www.toronto.ca/legdocs/mmis/2022/ey/bgrd/backgroundfile-223418.pdf

Motions

1 - Motion to Amend Item (Additional) moved by Councillor Stephen Holyday (Carried)

That:

 

1.  City Council amend Appendix A of the report so that it is better aligned with the Map of Appendix B, by removing the following streets:

 

a. Abinger Crescent

b. Appledale Road

c. Ashford Drive

d. North Heights Road


2 - Motion to Adopt Item as Amended moved by Councillor Mark Grimes (Carried)

Vote (Adopt Item as Amended) Apr-19-2022

Result: Carried Majority Required
Total members that voted Yes: 5 Members that voted Yes are Michael Ford, Mark Grimes (Chair), Stephen Holyday, Frances Nunziata, Anthony Perruzza
Total members that voted No: 0 Members that voted No are
Total members that were Absent: 0 Members that were absent are
Source: Toronto City Clerk at www.toronto.ca/council