IE25.16 - Wynford Drive Light Rail Transit Station Elevator Cost Estimate
- Decision Type:
- ACTION
- Status:
- Adopted
- Ward:
- 16 - Don Valley East
Committee Decision
The Infrastructure and Environment Committee received the report (October 12, 2021) from the General Manager, Transportation Services report for information.
Origin
(October 12, 2021) Report from the General Manager, Transportation Services
Summary
At its meeting held July 5th, 2021 for item 2021.IE23.18, it was requested that the General Manager, Transportation Services report back to the October 26, 2021 meeting of the Infrastructure and Environment Committee on the cost of building an elevator for residents to access the Eglinton Light Rail Transit from the Wynford community.
Based on a high level review, the capital cost to build and install an elevator is estimated to be $7,000,000 with a recurring annual cost of $50,000 in operating and maintenance costs.
Background Information
(October 12, 2021)
Report from the General Manager, Transportation Services on Wynford Drive Light Rail Transit Station Elevator Cost Estimate
https://www.toronto.ca/legdocs/mmis/2021/ie/bgrd/backgroundfile-171902.pdf
https://www.toronto.ca/legdocs/mmis/2021/ie/bgrd/backgroundfile-171902.pdf
Communications
(October 26, 2021) Letter from
Karl Frank (IE.Supp)
Motions
Motion
to Adopt Item
moved by
Deputy Mayor Denzil Minnan-Wong