Item - 2021.BA169.4
Tracking Status
- This item was considered by Bid Award Panel on December 22, 2021 and was adopted without amendment.
BA169.4 - Award of Ariba Document Number 3082157835 to The Municipal Infrastructure Group Ltd. for the Professional Engineering Services during Detailed Design, Construction, and Post Construction for Abandoning the Existing Transmission Watermains for Engineering and Construction Division
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- 3 - Etobicoke - Lakeshore, 11 - University - Rosedale, 12 - Toronto - St. Paul's
Panel Decision
The Bid Award Panel adopted the following:
1. Bid Award Panel grant authority to award the contract in accordance with the Contract Details set out in the report (December 16, 2021) from the Chief Procurement Officer:
Solicitation Number:
Request for Proposal, Ariba Document Number 3082157835, Contract Number RFP-21ECS-LU-03TT
Description:
Professional Engineering Services during Detailed Design, Construction and Post Construction for Abandoning the Existing Transmission Watermains on Boulton Drive, St. George Street and Seventh Street and Road Resurfacing on Boulton Drive and Seventh Street.
Recommended Supplier:
The Municipal Infrastructure Group Ltd.
Contract Award Value:
$2,048,529 net of all applicable taxes and charges
$2,314,838 including HST and all applicable charges
$2,084,583 net of HST recoveries
Contract is expected to start on January 1, 2022 and end on February 28, 2027.
Origin
Summary
Solicitation Issued: August 30, 2021 Solicitation Closed: October 8, 2021
Number of Addenda Issued: Nine (9)
Number of Bids: Two (2)
Table 2: Summary of Proposals Received
|
Supplier Name |
|
CIMA Canada Inc |
|
The Municipal Infrastructure Group Ltd |
Background Information
https://www.toronto.ca/legdocs/mmis/2021/ba/bgrd/backgroundfile-174514.pdf
Motions
Moved by Stephanie Fernandes.
Vote (Adopt Item)
|
Result: |
Majority Required |
|
Yes: |
Stephanie Fernandes, David McLeod, Anita Pathmanathan |
|
No: |
|
|
Absent: |
Jay Paleja (Chair) |