Item - 2021.BA143.3
Tracking Status
- This item was considered by Bid Award Panel on July 7, 2021 and was adopted without amendment.
BA143.3 - Award of Ariba Doc Number 2836830921 to Drainstar Contracting Ltd., for Basement Flooding Protection Program, Phase 4, Assignments 19-11 and 19-32 for Engineering and Construction Services
- Decision Type:
- ACTION
- Status:
- Adopted
- Ward:
- 6 - York Centre
Panel Decision
The Bid Award Panel adopted the following:
1. Bid Award Panel grant authority to award the contract in accordance with the Contract Details set out in the report (June 30, 2021) from the Chief Procurement Officer:
Solicitation Number:
Request for Tender, Ariba Doc Number 2836830921, Contract Number 19ECS-LU-12FP
Description:
Construction of sewer upgrades and related improvements for Basement Flooding Protection Program Phase 4, Assignments 19-11 and 19-32 on Brighton Ave., Clifton Ave., Combe Ave., Elder St., Goddard St., Hove St., Maxwell St., Overbrook Pl., Searle Ave., Shaftesbury St., and Sheppard Ave W.
Recommended Supplier:
Drainstar Contracting Ltd.
Contract Award Value:
$13,601,092 net of all applicable taxes and charges
$15,369,234 including HST and all applicable charges
$13,840,471 net of HST recoveries
Contract is expected to start on August 9, 2021 and end on December 31, 2023.
Origin
Summary
Solicitation Issued: February 24, 2021 Solicitation Closed: April 14, 2021
Number of Addenda Issued: Eight (8)
Number of Bids: Eight (8)
Table 2: Summary of Bids Received for Ariba Doc Number 2836830921 including bid price
|
Supplier Name |
Bid Price (Including H.S.T) |
|
Drainstar Contracting Ltd. |
$13,014,208.87* |
|
Comer Group Limited |
$14,439,486.35 |
|
614128 Ontario Ltd. (Trisan Construction) |
$16,436.918.98 |
|
GFL Infrastructure Group Inc. |
$16,520,356.26 |
|
Varcon Construction Corporation |
$17,186,681.49 |
|
Clearway Construction Inc. |
$18,005,605.59 |
|
KAPP Infrastructure Inc. |
$19,170,313.27 |
|
Memme Excavation Company Limited |
$22,350,930.46 |
* Pursuant to the Request for Tender document the contract award value includes contingency.
Background Information
https://www.toronto.ca/legdocs/mmis/2021/ba/bgrd/backgroundfile-168904.pdf
Motions
Moved by Stephanie Fernandes.
Vote (Adopt Item)
|
Result: |
Majority Required |
|
Yes: |
Jay Paleja (Chair), Stephanie Fernandes, David McLeod, Anita Pathmanathan |
|
No: |
|
|
Absent: |
|