Item - 2020.TE14.39
Tracking Status
- City Council adopted this item on June 29 and 30, 2020 with amendments.
- This item was considered by the Toronto and East York Community Council on March 12, 2020 and adopted without amendment. It will be considered by City Council on June 29 and 30, 2020.
TE14.39 - Construction Staging Area Time Extension - 387-403 Bloor Street East
- Decision Type:
- ACTION
- Status:
- Amended
- Ward:
- 13 - Toronto Centre
City Council Decision
City Council on June 29 and 30, 2020 adopted the following:
1. City Council authorize the continuation of the south sidewalk and a 2.8 metre wide portion of the eastbound curb lane on Bloor Street East, between a point 26 metres west of Sherbourne Street and a point 41 metres further west and provision of a temporary pedestrian walkway within the closed portion of the eastbound curb lane, from July 1, 2020 to March 8, 2021.
2. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.
3. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.
4. City Council direct the applicant to continue sweeping the construction site daily and nightly, or more frequently as needed to be cleared of any construction debris and made safe.
5. City Council direct the applicant to continue pressure washing the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe.
6. City Council direct the applicant to continue ensuring that the existing sidewalks or the proposed pedestrian walkway have proper lighting to ensure safety and visibility at all times of the day and night.
7. City Council direct the applicant to continue consulting and communicating all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications.
8. City Council direct the applicant to continue installing appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times.
9. City Council direct that Bloor Street East be returned to its pre-construction traffic and parking regulations when the project is complete.
Background Information (Community Council)
https://www.toronto.ca/legdocs/mmis/2020/te/bgrd/backgroundfile-146625.pdf
Motions (City Council)
That in accordance with the provisions of Chapter 27, Council Procedures, City Council reconsider Item TE14.39.
That City Council amend Toronto and East York Community Council Recommendation 1 by deleting the date "March 6, 2020" and inserting the date "July 1, 2020" so that it now reads as follows:
1. City Council authorize the continuation of the south sidewalk and a 2.8 metre wide portion of the eastbound curb lane on Bloor Street East, between a point 26 metres west of Sherbourne Street and a point 41 metres further west and provision of a temporary pedestrian walkway within the closed portion of the eastbound curb lane, from July 1, 2020 to March 8, 2021.
TE14.39 - Construction Staging Area Time Extension - 387-403 Bloor Street East
- Decision Type:
- ACTION
- Status:
- Adopted
- Ward:
- 13 - Toronto Centre
Community Council Recommendations
The Toronto and East York Community Council recommends that:
1. City Council authorize the continuation of the south sidewalk and a 2.8 metre wide portion of the eastbound curb lane on Bloor Street East, between a point 26 metres west of Sherbourne Street and a point 41 metres further west and provision of a temporary pedestrian walkway within the closed portion of the eastbound curb lane, from March 6, 2020 to March 8, 2021.
2. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.
3. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.
4. City Council direct the applicant to continue sweeping the construction site daily and nightly, or more frequently as needed to be cleared of any construction debris and made safe.
5. City Council direct the applicant to continue pressure washing the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe.
6. City Council direct the applicant to continue ensuring that the existing sidewalks or the proposed pedestrian walkway have proper lighting to ensure safety and visibility at all times of the day and night.
7. City Council direct the applicant to continue consulting and communicating all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications.
8. City Council direct the applicant to continue installing appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times.
9. City Council direct that Bloor Street East be returned to its pre-construction traffic and parking regulations when the project is complete.
Origin
Summary
As the Toronto Transit Commission (TTC) operates a transit service on Bloor Street East, City Council approval of this report is required.
SkyGrid Construction Incorporated is constructing a 54-storey residential building and a 10-story hotel building at 387-403 Bloor Street East. The development site will have frontage on both Bloor Street East and Selby Street. The site is located on the south side of Bloor Street East, one property east of Sherbourne Street. The sidewalk and a portion of the eastbound curb lane on the south side of Bloor Street East fronting the site are currently closed to accommodate construction staging operations for the development.
City Council, at its meeting on February 26, 2019, approved the subject construction staging area on Bloor Street East, from March 5, 2019 to March 5, 2020. A time extension of the construction staging area on Bloor Street East for an additional 20 months is required, in order to complete the construction of the development. However, Transportation Services is seeking authority for only 12 months (i.e. March 6, 2020 to March 8, 2021) at this time. Staff will review the need to further the duration of the construction staging area and seek authority from City Council, if necessary.
Background Information
https://www.toronto.ca/legdocs/mmis/2020/te/bgrd/backgroundfile-146625.pdf