GL19.15 - Emergency Non-Competitive Contract with Century Group Incorporated for Construction Management Services at the East Wing of Union Station

Decision Type:
ACTION
Status:
Adopted on Consent
Ward:
10 - Spadina - Fort York

City Council Decision

City Council on December 16, 17 and 18, 2020, adopted the following:

 

1. City Council receive the report (November 27, 2020) Report from the Executive Director, Corporate Real Estate Management, and the Chief Procurement Officer, Purchasing and Materials Management for information.

Background Information (Committee)

(November 27, 2020) Revised Report from the Executive Director, Corporate Real Estate Management, and the Chief Procurement Officer, Purchasing and Materials Management on Emergency Non-Competitive Contract with Century Group Incorporated for Construction Management Services at the East Wing of Union Station
https://www.toronto.ca/legdocs/mmis/2020/gl/bgrd/backgroundfile-159035.pdf
(November 16, 2020) Report from the Executive Director, Corporate Real Estate Management, and the Chief Procurement Officer, Purchasing and Materials Management on Emergency Non-Competitive Contract with Century Group Incorporated for Construction Management Services at the East Wing of Union Station
https://www.toronto.ca/legdocs/mmis/2020/gl/bgrd/backgroundfile-158541.pdf

GL19.15 - Emergency Non-Competitive Contract with Century Group Incorporated for Construction Management Services at the East Wing of Union Station

Decision Type:
ACTION
Status:
Adopted
Ward:
10 - Spadina - Fort York

Committee Recommendations

The General Government and Licensing Committee recommends that:  

 

1. City Council receive the report (November 27, 2020) Report from the Executive Director, Corporate Real Estate Management, and the Chief Procurement Officer, Purchasing and Materials Management for information.

Origin

(November 16, 2020) Report from the Executive Director, Corporate Real Estate Management, and the Chief Procurement Officer, Purchasing and Materials Management

Summary

The purpose of the report is to inform the General Government and Licensing Committee regarding an emergency non-competitive contract that the City has entered into with Century Group Inc. under Purchase Order No. 6051271, to provide emergency structural remediation services at the East Wing of Union Station, in the amount of $2,968,877.09 net of Harmonized Sales Tax ($3,021,129.33 net of Harmonized Sales Tax recoveries).

 

As a result of the demolition undertaken as part of the Workplace Modernization Program to create office swing space at Union Station, it was discovered that there were significant structural issues with the roof and the floor and ceiling slabs of the second, third and fourth floors in the East Wing of Union Station. Once discovered, the structural issues needed to be addressed immediately, as required by the Ontario Building Code, to prevent possible collapse, and to ensure the safety of all personnel on site. The structural issues could not have been found by any due diligence processes prior to construction, as only full demolition exposed the structural issues.

 

Reporting back to City Council is required in accordance with Municipal Code Chapter 195, Purchasing, Article 7, Section 195-7.4(B) where a non-competitive contract over $500,000 was entered into on the basis of emergency. 

Background Information

(November 27, 2020) Revised Report from the Executive Director, Corporate Real Estate Management, and the Chief Procurement Officer, Purchasing and Materials Management on Emergency Non-Competitive Contract with Century Group Incorporated for Construction Management Services at the East Wing of Union Station
https://www.toronto.ca/legdocs/mmis/2020/gl/bgrd/backgroundfile-159035.pdf
(November 16, 2020) Report from the Executive Director, Corporate Real Estate Management, and the Chief Procurement Officer, Purchasing and Materials Management on Emergency Non-Competitive Contract with Century Group Incorporated for Construction Management Services at the East Wing of Union Station
https://www.toronto.ca/legdocs/mmis/2020/gl/bgrd/backgroundfile-158541.pdf

Motions

Motion to Adopt Item moved by Councillor Stephen Holyday (Carried)