EX17.8 - Toronto Water 2020 Capital Budget and 2021-2029 Capital Plan Adjustments
- Decision Type:
- ACTION
- Status:
- Adopted on Consent
- Wards:
- All
City Council Decision
City Council on October 27, 28 and 30, 2020, adopted the following:
1. City Council authorize the reallocation of cashflows within the Toronto Water Approved 2020 Capital Budget and 2021-2029 Capital Plan in the amount of $52.234 million, for acceleration and deferral of projects, as presented in Schedule A (Part A and B) to the report (September 24, 2020) from the General Manager, Toronto Water with a zero Budget impact.
2. City Council authorize the reallocation of project costs and cashflows in the Toronto Water Approved 2020 Capital Budget and 2021-2029 Capital Plan in the amount of $6.169 million from projects that have been awarded under budget or completed to those requiring additional funding in the same amount as presented in Schedule A (Part C) to the report (September 24, 2020) from the General Manager, Toronto Water with a zero Budget impact.
Background Information (Committee)
https://www.toronto.ca/legdocs/mmis/2020/ex/bgrd/backgroundfile-157656.pdf
(September 24, 2020) Report from the General Manager Toronto Water on Toronto Water 2020 2020-10-08 Decision Letter - Budget Committee Page 1 of 2 Capital Budget and 2021-2029 Capital Plan Adjustments
https://www.toronto.ca/legdocs/mmis/2020/ex/bgrd/backgroundfile-157658.pdf
Schedule A - Part A - Toronto Water 2020-2021 Budget Adjustments Reallocations due to Accelerations, Part B - Toronto Water 2020-2021 Budget Adjustments Reallocations due to Deferrals and Part C - Toronto Water 2020-2021 Budget Adjustments Reallocations
https://www.toronto.ca/legdocs/mmis/2020/ex/bgrd/backgroundfile-157659.pdf
EX17.8 - Toronto Water 2020 Capital Budget and 2021-2029 Capital Plan Adjustments
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
Committee Recommendations
The Executive Committee recommends that:
1. City Council authorize the reallocation of cashflows within the Toronto Water Approved 2020 Capital Budget and 2021-2029 Capital Plan in the amount of $52.234 million, for acceleration and deferral of projects, as presented in Schedule A (Part A and B) to the report (September 24, 2020) from the General Manager, Toronto Water with a zero Budget impact.
2. City Council authorize the reallocation of project costs and cashflows in the Toronto Water Approved 2020 Capital Budget and 2021-2029 Capital Plan in the amount of $6.169 million from projects that have been awarded under budget or completed to those requiring additional funding in the same amount as presented in Schedule A (Part C) to the report (September 24, 2020) from the General Manager, Toronto Water with a zero Budget impact.
Origin
Summary
This report requests City Council's authority to amend Toronto Water's Approved 2020 Capital Budget and 2021-2029 Capital Plan by adjusting project cash flows contained within the Budget and Plan, respectively, to align forecasted project accelerations and deferrals. Additional reallocations to project cashflows and project costs are requested where additional project costs exceed the current approved cashflow. These reallocations will allow Toronto Water to continue to deliver projects within its capital plan. The adjustments will have a zero dollar impact on the 2020 Capital Budget and 2021-2029 Capital Plan and will align the budget and plan with Toronto Water's capital project delivery schedule and program requirements.
Background Information
https://www.toronto.ca/legdocs/mmis/2020/ex/bgrd/backgroundfile-157656.pdf
(September 24, 2020) Report from the General Manager Toronto Water on Toronto Water 2020 2020-10-08 Decision Letter - Budget Committee Page 1 of 2 Capital Budget and 2021-2029 Capital Plan Adjustments
https://www.toronto.ca/legdocs/mmis/2020/ex/bgrd/backgroundfile-157658.pdf
Schedule A - Part A - Toronto Water 2020-2021 Budget Adjustments Reallocations due to Accelerations, Part B - Toronto Water 2020-2021 Budget Adjustments Reallocations due to Deferrals and Part C - Toronto Water 2020-2021 Budget Adjustments Reallocations
https://www.toronto.ca/legdocs/mmis/2020/ex/bgrd/backgroundfile-157659.pdf