Item - 2019.ZB4.5
Tracking Status
- This item was considered by Board of Management of the Toronto Zoo on June 13, 2019 and was adopted without amendment.
ZB4.5 - Front Entrance and Welcome Area
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
Board Decision
The Board of Management of the Toronto Zoo:
1. Recommended that the contract for architectural, engineering, and contract administration services for the Front Entrance and Welcome area concept design, detailed design, and contract administration be awarded to Zeidler Architect Inc. in the amount of $1,535,312.64 including fees, disbursements, contingency and all applicable taxes.
Origin
(May 30, 2019) Report from the Director, Facilities and Infrastructure, Toronto Zoo
Summary
This report recommends the award of a contract for architectural, engineering, and contract administration services for the Front Entrance and Welcome Area project.
Background Information
(May 30, 2019)
Report and Schedule 1 from the Director, Facilities and Infrastructure, Toronto Zoo on Front Entrance and Welcome Area
https://www.toronto.ca/legdocs/mmis/2019/zb/bgrd/backgroundfile-133810.pdf
https://www.toronto.ca/legdocs/mmis/2019/zb/bgrd/backgroundfile-133810.pdf
Motions
Motion
to Adopt Item
moved by
Councillor Cynthia Lai
(Carried)