Item - 2019.TE9.42
Tracking Status
- This item was considered by Toronto and East York Community Council on October 10, 2019 and was adopted without amendment. City Council has delegated authority for this matter to the Toronto and East York Community Council and therefore, the decision is final.
TE9.42 - Construction Staging Area Time Extension - Hazelton Avenue - 128 Hazelton Avenue
- Decision Type:
- ACTION
- Status:
- Adopted
- Schedule Type:
- Delegated
- Ward:
- 11 - University - Rosedale
Community Council Decision
The Toronto and East York Community Council:
1. Authorized the continuation of the closure of the west sidewalk and a 2.6 metre wide portion of the northbound lane on Hazelton Avenue, between Davenport Road and a point 32 metres south, from November 1, 2019 April 30, 2020.
2. Directed the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.
3. Directed the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.
4. Directed that Hazelton Avenue be returned to its pre-construction traffic and parking regulations when the project is complete.
Origin
Summary
This staff report is about a matter that Community Council has delegated authority to make a final decision, provided that it is not amended so that it varies with City policy or by-laws.
Clark Construction Management is constructing a 9-storey condominium building at 128 Hazelton Avenue. The site is located in the south-west corner of Davenport Road and Hazelton Avenue. Construction staging areas for the development have been set up on the south side of Davenport Road and the west side of Hazelton Avenue.
Toronto and East York Community Council, at its meeting on January 16, 2018, approved the subject construction staging area on Hazelton Avenue, from February 7, 2018 to October 31, 2019. Transportation Services is requesting approval to extend the duration of the construction staging area on Hazelton Avenue for an additional six months - i.e. from November 1, 2019 to April 30, 2020 - in order to complete the construction of the development.
The developer has requested an extension of the duration of the construction staging area on Hazleton Avenue, as the site has experienced a number of construction delays due ground water contamination and site logistics issues.