Item - 2019.TE9.40

Tracking Status

  • This item was considered by Toronto and East York Community Council on October 10, 2019 and was adopted without amendment. City Council has delegated authority for this matter to the Toronto and East York Community Council and therefore, the decision is final.

TE9.40 - Construction Staging Area Time Extension - Phase 2 and 3 - Markham Street - Mirvish Village

Decision Type:
ACTION
Status:
Adopted
Schedule Type:
Delegated
Ward:
11 - University - Rosedale

Community Council Decision

The Toronto and East York Community Council:

 

1. Authorized the continuation of the full closure of Markham Street, between Bloor Street West and Lennox Street, from November 1, 2019 to December 31, 2021.

 

2. Directed the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

3. Directed the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.

 

4. Directed that Markham Street be returned to its pre-construction traffic and parking regulations when the project is complete.

Origin

(September 18, 2019) Report from the Acting Director, Traffic Management, Transportation Services

Summary

This staff report is about a matter that Community Council has delegated authority to make a final decision, provided that it is not amended so that it varies with City policy or by-laws.

 

Westbank Projects Corp. is currently redeveloping a number of properties located in the south-west quadrant of Bloor Street West and Bathurst Street and Bloor Street West and Markham Street. A temporary full closure of Markham Street, between Bloor Street West and Lennox Street is in effect to accommodate construction staging operations for the development.

 

Toronto and East York Community Council, at its meeting on October 17, 2017, approved the subject construction staging area on Markham Street, from October 24, 2017 to October 31, 2019. A time extension of the construction staging area on Markham Street has been requested for an additional 26 months (i.e., November 1, 2019 to December 31, 2021), in order to complete the construction of the development.

Background Information

(September 18, 2019) Report and Attachment 1 from the Acting Director, Traffic Management, Transportation Services - Construction Staging Area Time Extension - Phase 2 and 3 - Markham Street - Mirvish Village
https://www.toronto.ca/legdocs/mmis/2019/te/bgrd/backgroundfile-138409.pdf

Motions

Motion to Adopt Item moved by Councillor Joe Cressy (Carried)
Source: Toronto City Clerk at www.toronto.ca/council