Item - 2019.TE4.51
Tracking Status
- This item was considered by Toronto and East York Community Council on March 19, 2019. The Toronto and East York Community Council postponed consideration of this item. Consult the text of the decision for further information on the deferral.
TE4.51 - Construction Staging Area - 177 Front Street East
- Decision Type:
- ACTION
- Status:
- Deferred
- Ward:
- 13 - Toronto Centre
Community Council Decision
The Toronto and East York Community Council deferred consideration of the item until its April 24, 2019 meeting.
Origin
Summary
As the Toronto Transit Commission (TTC) operates a transit service on Princess Street City Council approval of this report is required.
Saddlebrook Management Consultants Inc., is constructing a 30-storey mix-use condominium building with 1531 units, with one level underground parking facility at 177 Front Street East. The site is bounded by The Esplanade to the south, Front Street East to the north, Princess Street to the east and Lower Sherbourne Street to the west.
Transportation Services is requesting approval to close the sidewalk and the southbound parking lane on the west side of Princess Street for a period of 47 months. Pedestrian movements will be accommodated on the east side of Princess Street as there are no pedestrian generators on the west side.
Background Information
https://www.toronto.ca/legdocs/mmis/2019/te/bgrd/backgroundfile-130363.pdf
Communications
https://www.toronto.ca/legdocs/mmis/2019/te/comm/communicationfile-92454.pdf
Motions
That consideration of the item be deferred until April 24, 2019 meeting.